Calculate the total production costs of the disney project

Assignment Help Managerial Accounting
Reference no: EM132523769

Walt Favourites manufactures a wide variety of birthday decorative items. Walt's activity-based costing overhead rates are:

Purchasing $250 per order

Storing $8 per square metre

Machining $60 per machine hour

Supervision $20 per direct labour hour

The Disney's 75th Birthday Project involved five purchase orders, 2,000 square metres, 45 machine hours, and 25 direct labour hours. The cost of direct materials on the job was $35,000 and the direct labour rate is $15 per hour.

Question a) Calculate the total production costs of the Disney Project using activity-based costing.

Question b) Calculate the total production costs of the Disney Project using traditional costing, when manufacturing overhead is applied at 125% of direct labour cost.

Reference no: EM132523769

Questions Cloud

General requirements for informed consent : A description of any reasonably foreseeable risks or discomforts to the subject. Disclosure of appropriate alternative procedures or courses of treatment
General requirements for informed consent : A description of any reasonably foreseeable risks or discomforts to the subject. Disclosure of appropriate alternative procedures or courses of treatment
How well disney has managed labour costs : Diane Disney, Explain to the COO, who has been on job, what your analysis shows about how well Disney has managed her labour costs.
Calculate the total production costs of the disney project : Calculate the total production costs of the Disney Project using traditional costing, when manufacturing overhead is applied at 125% of direct labour cost.
Calculate the total production costs of the disney project : Calculate the total production costs of the Disney Project using traditional costing, when manufacturing overhead is applied at 125% of direct labour cost.
How well disney has managed labour costs : Diane Disney, Explain to the COO, who has been on job, what your analysis shows about how well Disney has managed her labour costs.
Calculate the total production costs of the disney project : Calculate the total production costs of the Disney Project using traditional costing, when manufacturing overhead is applied at 125% of direct labour cost.
How well disney has managed labour costs : Diane Disney, Explain to the COO, who has been on job, what your analysis shows about how well Disney has managed her labour costs.
10-year loan with a 20- year amortization schedule : A property has a maturing loan and needs to be refinanced. It is appraised at $25 million based on a cap rate of 6%.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd