Calculate the total overhead flexible budget variance

Assignment Help Cost Accounting
Reference no: EM13962787

Manufacturing standard cost sheets

One of your clients, Moore Manufacturing has asked you to assist them in evaluating their performance against their budgets. The management of Moore Manufacturing has provided the following standard cost sheet for one of its products:

Direct Materials 6 lb @ $2 per pound $12
Direct Labor 3 hrs @ $25 per hr $75
Variable factor overhead 2 hrs @ $4 per hour $8
Fixed factory overhead 2 hr @ $15 per hour $30
Cost per unit   $125

Moore Manufacturing applies factory overhead based on direct labor hours and factory overhead is allocated based on a practical capacity of 500 units of product.

The actual operating results for the year are as follows:

Units manufactured   400
Direct materials purchased and used 1,800 pounds $19,800
Direct labor incurred 750 hours 20,250
Variable factory overhead incurred   5,000
Fixed factory overhead incurred   15,800

Determine the following for the period:

Flexible budget for variable overhead based on output for the period

Total variable overhead applied to production during the period

Total budgeted fixed factory overhead

Total fixed factory overhead applied to production during the period

Calculate the following variances using four-variance analysis:

Total variable overhead variance

Variable overhead spending variance

Variable overhead efficiency variance

Total under applied or over applied variable overhead

Fixed overhead spending variance

Production volume variance

Total fixed overhead variance

Total under applied or over applied fixed overhead

Calculate the following variances using three-variance analysis:

Factory overhead spending variance

Factory overhead efficiency variance

Production volume variance

Calculate the total overhead flexible budget variance and the production volume variance using a two-variance analysis.

Part Two:

In a 750 word document, explain to the management team at Moore Manufacturing about the variances and evaluation of their performance

Reference no: EM13962787

Questions Cloud

What questions do you have about apa format and style : What questions do you have about APA format and style? Where might you search for answers to these questions? What steps will you take to ensure that the work you submit meets APA format and style expectations? (This response does not require researc..
Best mix of large and small globes : Your company works 1 shift, 40 hours per week, 40 hours for the kiln and 40 hours for the spray paint equipment. Plot the constraints. Show the feasible region. What is the best mix of large and small globes to make the most profit?
Research paper on port facility operations and security : You are to prepare a research paper (Times New Roman, Font 12-double space) on Port Facility Operations and Security using APA style format
What strategy should you pursue in the bond market : What strategy should you pursue in the bond market to position yourself to profit from your beliefs?
Calculate the total overhead flexible budget variance : Calculate the total overhead flexible budget variance and the production volume variance using a two-variance analysis.
What are the main planning tasks performed : How does having a scope and WBS help project teams during project execution? Why is it difficult to develop good plans - Name the main planning tasks performed as part of project integration management
What is the ratio of the speed of the water flowing : A meter long hose of 14cm diameter is connected to a second hose which is 4 meters long and 7cm in diameter. At the open end of the second hose water flows out at a rate of 8 cm^3/sec. What is the ratio of the speed of the water flowing in the se..
Who wrote the plan - the virginia plan : In this assignment you will summarize the major plans that impacted the creation of the Constitution: The Virginia Plan and The New Jersey Plan, Who wrote the plan? Who benefited from the plan? What specific powers will the congress have
How far would the water disperse the larger mass of the pool : A long lance 38mm ID mounted vertically into a pool the last 300mm of the lance is bent 45 deg, so the end of the lance is 305mm above the pool floor. Would fitting a nozzle or several small nozzles to the lance head improve the dispersal rate?

Reviews

Write a Review

Cost Accounting Questions & Answers

  Cost accounting assignment

Evaluate Method of measuring costs associated with production, budgeting process, normal job-order costing system , master budget, cycle time.

  Prepare the journal entries

Prepare the journal entries to record the bond issue and interest expense.

  Advise as to the liability of all the parties

Write a report on given case study and Advise as to the liability of ALL the parties both under common law and the Corporations Law.

  Prepare revenues budget

Prepare Revenues budget and Production budget in units

  Effect of exchange rate changes on cash and cash

Effect of exchange rate changes on cash and cash

  Corporate governance

You are to reflect on how this case of China Sky relates to what the arguments for and against allowing audit firm partners and/or employees to join audit committees.

  Cost-benefit analysis

A cost-benefit analysis of electronic medical records in primary care

  Non-annual interest rates and annuities

Theory of Interest- Non-annual interest rates and annuities

  Job costing in service organizations

How is job costing in service organizations different from job costing in manufacturing environments?

  Accounting for bad debt expense

Accounting for bad debt expense

  Accounting and partnership problems

Accounting and Partnership problems

  Development of relevant cash flows

Development of relevant cash flows - Cost estimating and financial analysis

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd