Reference no: EM132583027
Anchor Homes Ltd manufactures modular homes. The company has two main products that it sells commercially: a 1,000 square foot, one-bedroom model and a 1,500 square foot, two-bedroom model. The company recently began providing emergency housing (huts) to Emergency Management Australia (EMA). The emergency housing is similar to the 1,000 square foot model.
EMA has requested Anchor Homes Ltd to make a bid for 150 emergency huts to be sent for flood victims in the east. Your boss has asked that you produce this bid. In preparing the bid, you find a recent invoice to EMA for 200 huts provided after tropical cyclone Debbie. You also have a standard cost sheet for the 1,000 square foot model sold commercially.
Both are provided as follows:
Standard cost sheet: 1,000 sq. ft. one-bedroom model
Direct materials $8,000
Direct manufacturing labour (30 hours) 600
Manufacturing overhead* ($3 per direct labour dollar) 1,800
Total cost $10,400
Retail markup on total cost 20%
Retail price $12,480
- Overhead cost pool includes inspection labour ($15 per hour), setup labour ($12 per hour), and other indirect costs
INVOICE:
DATE: September 15, 2017 BILL TO: EMA
FOR: 200 Emergency Huts
SHIP TO: Townsville, Queensland
Direct materials $1,840,000
Direct manufacturing labour 138,400
Manufacturing overhead 415,200
Total cost 2,393,600
Government contract markup on total cost 15%
Total due $2,752,640
- Direct manufacturing labour includes 28 production hours per unit, 4 inspection hours per unit, and 6 setup hours per unit
Required:
Question 1. Calculate the total bid if you base your calculations on the standard cost sheet assuming a cost plus 15% government contract.
Question 2. Calculate the total bid if you base your calculations on the September 15, 2017, invoice assuming a cost plus 15% government contract.
Question 3. What are the main discrepancies between the bids you calculated in #1 and #2?
Question 4. What bid should you present to your boss? What principles from the CIMA's Code of Ethics should guide your decision?