CASE STUDY
Please read the case study given below and answer the questions given at the end.
Systems Software (P) ltd. is planning to develop new software. It has identified the activities in the table below for this software development project and has calculated three times estimates in days for each of the activity.
Activity
Description
Predecessors
Optimistic Time
Most Likely Time
Pessimistic Time
A
Create Objective
-
1
2
3
B
Choose Operating System
5
7
C
Generate Algorithm
6
10
14
D
Choose a Suitable Programming
4
8
E
Write the Program
B,C,D
9
F
Test the Software
G
Get Approval for Commercialization
Questions:
1. Draw the network diagram; find out the critical path and the expected duration of the project.
2. Calculate the slack time for each of the activities.
3. Calculate the probability of completing the project in 30 days.
One unit of D costs $20 to make and demand is estimated to be 30 - .14 * Price of D. The utilization of labor and materials and the available quantity of resources is shown in the table. A reasonable price for the products is between 90 and 140.
Solve the following problems: Find the optimal solution and graph. Please show all work:
Many software companies, after years of providing unlimited free telephone technical support for their products, began to charge for these services (typically after an initial start-up period of 90 days). Most companies offer two pricing plans.
Show the B&B tree.If node is fathomed,indicate why it is fathomed.Provide the sequence of problems solved,. eg. P1-P3-P4, etc.Clearly indicate what the optimal solution is. Note: x4 does not have to be integer.After solving the root node, branch o..
fourier seriesa fourier series may be truncated to the formfor each of the following functions nd the fourier coecients
A wire 10 feet long is to be cut into two pieces, each of which is to formed into a square. What is the largest possible total area of the two squares? What is the smallest possible total area?
Dirichlet series
1. daily airlines fies from amsterdam to london every day. the price of a ticket for this extremely popular flight
Every convergent sequence contains either an increasing, or a decreasing subsequence.
Heating is effected in a gas-fired furnace, where products of combustion at T8 = 800°C maintain a convection coefficient of h = 250 W/m2 · K on both surfaces of the plate. How long the plate should be left in the furnace?
Formulate the Linear Programming model for this problem. Solve the problem using Excel Solver or QM for Windows.
Construct a frequency distribution. Construct a relative frequency distribution. Construct a frequency histogram of the data.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd