Systems Software (P) ltd. is planning to develop new software. It has identified the activities in the table below for this software development project and has calculated three times estimates in days for each of the activity.

Activity

Description

Predecessors

Optimistic Time

Most Likely Time

Pessimistic Time

A

Create Objective

-

1

2

3

B

Choose Operating System

A

3

5

7

C

Generate Algorithm

A

6

10

14

D

Choose a Suitable Programming

A

4

6

8

E

Write the Program

B,C,D

8

9

10

F

Test the Software

E

2

4

6

G

Get Approval for Commercialization

F

1

3

5

Questions:

1. Draw the network diagram; find out the critical path and the expected duration of the project.

2. Calculate the slack time for each of the activities.

3. Calculate the probability of completing the project in 30 days.

Reference no: EM131083982

Questions Cloud

Battle of the alamo fought over : Q1: Who was the last to die at the battle of the alamo? Q2: What was the battle of the alamo fought over?
For an arbitrary random variable x : For an arbitrary random variable X, use the Chebyshev inequality to show that the probability that X is more than k standard deviations from its expected value E[X] satisfies
Sketch the spectrum of the sampled signal up to 20 khz : Sketch the recovered analog signal spectrum if an ideal low pass filter with a cutoff frequency of 4 kHz is used to filter the sampled signal in order to recover the original signal.
Mean darkness of cotton minus : Evidently one procedure gives darker colors than the other. Make a confidence interval estimate for the mean darkness of cotton minus the mean darkness of ramie after this dye procedure. Use 99% as your confidence level.
Calculate the slack time for each of the activities : Draw the network diagram; find out the critical path and the expected duration of the project. Calculate the slack time for each of the activities.
Future health care trends technologies innovation : Create a PowerPoint presentation (4-6 slides) outlining some options that the future may hold for Healing Hands Hospital.
What is the probability that they both get a hit : 1. What is the probability that Joey or Tommy will get a hit? 2. What is the probability that neither player gets a hit? 3. What is the probability that they both get a hit?
What is amount of the excess quantity supplied or demanded : If the present rental rate of one-bedroom apartments is $1,000 per month, through what mechanism will the rental rate adjust to the equilibrium rental rate of $800?
The weight of a randomly chosen maine black bear : The weight of a randomly chosen Maine black bear has expected value E[W] = 500 pounds and standard deviation σW = 100 pounds. Use the Chebyshev inequality to upper bound the probability that the weight of a randomly chosen bear is more than 200 pou..

Reviews

Write a Review

Engineering Mathematics Questions & Answers

  Reasonable price for the products

One unit of D costs $20 to make and demand is estimated to be 30 - .14 * Price of D. The utilization of labor and materials and the available quantity of resources is shown in the table. A reasonable price for the products is between 90 and 140.

  Find the optimal solution and graph

Solve the following problems: Find the optimal solution and graph. Please show all work:

  Providing unlimited free telephone technical support

Many software companies, after years of providing unlimited free telephone technical support for their products, began to charge for these services (typically after an initial start-up period of 90 days). Most companies offer two pricing plans.

  Problem regarding the branch and bound

Show the B&B tree.If node is fathomed,indicate why it is fathomed.Provide the sequence of problems solved,. eg. P1-P3-P4, etc.Clearly indicate what the optimal solution is. Note: x4 does not have to be integer.After solving the root node, branch o..

  Fourier seriesa fourier series may be truncated to the

fourier seriesa fourier series may be truncated to the formfor each of the following functions nd the fourier coecients

  What is the smallest possible total area

A wire 10 feet long is to be cut into two pieces, each of which is to formed into a square. What is the largest possible total area of the two squares? What is the smallest possible total area?

  Prime number theorem

Dirichlet series

  1 daily airlines fies from amsterdam to london every day

1. daily airlines fies from amsterdam to london every day. the price of a ticket for this extremely popular flight

  Proof of bolzano-weierstrass to prove the intermediate value

Every convergent sequence contains either an increasing, or a decreasing subsequence.

  Maintain a convection coefficient

Heating is effected in a gas-fired furnace, where products of combustion at T8 = 800°C maintain a convection coefficient of h = 250 W/m2 · K on both surfaces of the plate. How long the plate should be left in the furnace?

  Formulate the linear programming model for given problem

Formulate the Linear Programming model for this problem. Solve the problem using Excel Solver or QM for Windows.

  Construct a frequency distribution

Construct a frequency distribution. Construct a relative frequency distribution. Construct a frequency histogram of the data.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd