Levy Furniture, a furniture manufacturer is planning a factory expansion project. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. The project network is also provided.

Activity

Description

Immediate Predecessors

Optimistic Time (days)

Most Likely Time (days)

Pessimistic Time (days)

A

Develop initial plans

--

2

2.5

6

B

Secure financing

A

1

2

3

C

Develop final plans

A

2

3

10

D

Hire contractor

C

1

3

5

E

Secure permits

C

1

4

7

F

Construct addition

B,D,E

3

11

13

G

Order equipment

A

6

11

22

H

Install equipment

F,G

1

3

5

a) Construct the project network.

b) Identify the critical path and provide the project completion time.

c) Calculate the slack time for each activity and for each path (relative to the critical path).

d) Looking at only the critical path, find the probability that the store will take more than 23 working days to open.

e) What is the probability of completing path AGH in time for the store to open within 23 working days?

Reference no: EM13523082

Questions Cloud

Find how many gas molecules does the flask contain : An open flask sitting in a lab fridge looks empty, but we know that actually it is filled with a mixture of gasses called air. how many gas molecules does the flask contain
Determine the sequence of jobs using the rules : Determine the sequence of jobs using the rules - Prioritize the rules used in based on average flow time measured from now.
Explain pressure conditions will cause a gas to exhibit : Which set of temperature and pressure conditions will cause a gas to exhibit the LEAST deviation from ideal gas behavior
Obtain the coefficient of volume expansion of this substance : You heat a 545 cm^3 sample of a substance from 121 celcius to 285 celcius and find that its volume increases by 2.29 cm^3. obtain the coefficient of volume expansion of this substance
Calculate the slack time for each activity : Calculate the slack time for each activity and for each path and looking at only the critical path, find the probability that the store will take more than 23 working days to open.
Capital balances as of the end of the current year : Capital balances as of the end of the current year:
Explain what is the molar mass of an ideal gas : What is the molar mass of an ideal gas if a 0.800 g sample of this gas occupies a volume of 200. mL at 50.0 oC and 720. mm Hg
Cases of relays and capacitors : How many cases of relays and capacitors should Harkin Electronics produce during that period? If your answer is in fractional units of cases that is acceptable - do not round to whole number of cases.
Explain what volume in ml of 12 m hci solution : What volume (in mL) of 12 M HCI solution is required to prepare exactly 500. mL of a 0.45 M HCI solution

Reviews

Write a Review

Applied Statistics Questions & Answers

  Calculate mortgage rates and production lot size

Calculate mortgage rates, production lot size, forecast the demand for the products, track epidemics and their spread, help solve crimes, even help estimate tax revenues.

  Simulation of a poisson and a compound poisson process

Compute the expected time until the 100 th student arrives. What is the probability that the time between the arrival of the 200th and the 201st student exceeds 2 days?

  What is the outcome of the multivariate tests

Examine the skewness and kurtosis values for each dependent variable, examining the histograms and examine the Shapiro-Wilks' results and What is the outcome of the multivariate tests

  Calculate the median for the group of results

State the five types of central tendency in general use. Which of these are most frequently used in SPC work and calculate the median for the group of results tabulated below: 1,3,4,6,7,9,11,14,16,17,18.

  What research design was used this study

What research design was used this study

  Find the correlation between anca and the clinical

find the correlation between anca and the clinical manifestations k l c gi msk n ent s. nbspwe want to find out which

  You are expected to complete a project related to

you are expected to complete a project related to inferential statistics. the project must contain the following

  Calculating a z-score and graphing a box plot

Calculating a Z-score and graphing a box plot and Statistical Inference of Sample Mean , Binomial Distribution and Regression Analysis

  This assignment requires a considerable amount of computer

this assignment requires a considerable amount of computer work and written comment. you may need to seek guidance from

  1 find the equation of the regression line for the given

1. find the equation of the regression line for the given data.nbsp what is the predicted value of y when x -2?nbsp

  Find the correlation coefficient between x and y

Find the equation of the regression line for the given data.  What is the predicted value of Y when X = -2?  What is the predicted value of Y and find the correlation coefficient between X and Y.  Is there a weak or strong, positive or negative corr..

  Question 1 one subway station in toronto has 6 turnstiles

question 1 one subway station in toronto has 6 turnstiles each of which can be controlled by the station manager to be

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd