A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 60 percent complete. The planners were only expecting to be 50 percent through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,420,000 and it was done for only $1,300,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,500,000 but was actually done for $9,000,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,500,000. To date they have spent $5,000,000 on the superstructure.
Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.)
Schedule variance $________
Schedule performance index ________
Cost performance index ________
Topics related to supply chain management
: Research the following topics related to Supply Chain Management:
|
Survey problems and propose improvements
: My project is to survey problems and propose improvements at my new job as an employee (a dispatcher) at Flight Services and Systems (FSS) at Logan International Airport, Boston, Massachusetts. Find a video that describes a success story in an organi..
|
Create task development timeline
: Create a Task development timeline OR a Gantt chart for a LEAD POISONING PREVENTION PROGRAM to describe the timetable for implementing this proposed health promotion program.
|
Logic model for lead poisoning prevention program
: Create a logic model for a LEAD POISONING PREVENTION PROGRAM that illustrates this proposed health promotion program.
|
Calculate the schedule variance-schedule performance index
: A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third..
|
What is the reorder point
: The annual demand for a product is 5,000 units. The company orders 200 units each time an order is placed. The lead-time is 6 days, and the company has determined that 25 units should be held as a safety stock. There are 250 working days per year. Wh..
|
Money to allocate for soda-traditional soda advertising
: BP Cola must decide how much money to allocate for new soda and traditional soda advertising over the coming year. The advertising budget is $10,000,000. Because BP wants to push its new sodas, at least one-half of the advertising budget is to be dev..
|
The best combination of barrels of pruned and regular olives
: The seasonal yield of olives in a Piraeus, Greece, vineyard is greatly influenced by a process of branch pruning. If olive trees are pruned every two weeks, output is increased. The pruning process, however, requires considerably more labor then perm..
|
Discuss global supply chain and possible remedies
: Discuss Somerset's global supply chain and possible remedies for its supply chain problems, including strategic and tactical changes that might improve the company's supply chain performance, reduce system variability, and improve quality and custome..
|