Calculate the present value of net benefits of the project

Assignment Help Financial Management
Reference no: EM131903344

(Instructor-provided spreadsheet recommended.)

The following table gives cost and benefit estimates in real dollars for dredging a navigable channel from an inland port to the open sea.

Year

Dredging and Patrol Cost($)

Saving to Shippers($)

Value of Pleasure Boating($)

0

2,548,000

0

0

1

60,000

400,000

60,000

2

60,000

440,000

175,000

3

70,000

440,000

175,000

4

70,000

440,000

175,000

5

80,000

440,000

175,000

6

80,000

440,000

175,000

7

90,000

440,000

175,000


The channel would be navigable for seven years, after which silting would render it unnavigable. Local economists estimate that 75 percent of the savings to shippers would be directly invested by the firms or their shareholders, and the remaining 25 percent would be used by shareholders for consumption.

They also determine that all government expenditures come at the expense of private investment.The social marginal rate of time preference is assumed to be 1.5 percent, the marginal rate of return on private investment is assumed to be 4.5 percent, and the shadow price of capital is assumed to be 1.33.

Assuming that the costs and benefits accrue at the end of the year they straddle and using the market-based interest rate approach, calculate the present value of net benefits of the project using each of the following methods.

a. Discount at the marginal rate of return on private investment, as suggested by the U.S. Office of Management and Budget.

b. Discount at the social marginal rate of time preference, as suggested by the U.S. Environmental Protection Agency.

c. Discount using the shadow price of capital method.

d. Discount using the shadow price of capital method. However, now assume that the social marginal rate of time preference is 2.0 percent, rather than 1.5 percent.

e. Discount using the shadow price of capital method. However, now assume that the shadow price of capital is 1.1, rather than 1.33. Again assume that the social marginal rate of time preference is 1.5 percent.

f. Discount using the shadow price of capital method. However, now assume that only 50 percent of the savings to shippers would be directly invested by the firms or their shareholders, rather than 75 percent.

Again assume that the social marginal rate of time preference is 1.5 percent and that the shadow price of capital is 1.33.

Reference no: EM131903344

Questions Cloud

What is the duration of the bond : What is your expected return if you invest 40% of your money into the risk free rate at 5%and the remaining 60% in the minimum risk portfolio?
Write a procedure for creating the information : Write a procedure for creating and manipulating the information in a central structure store. Write a routine for storing information in a traversal state list.
Use as initial investment in fixed assets : What is the proper cash flow amount to use as the initial investment in fixed assets when evaluating this project?
Discuss the arbitration requirement : Must a complainant always file a complaint of illegal discrimination with the relevant state or local agency before filing a complaint with the EEOC?
Calculate the present value of net benefits of the project : Discount at the marginal rate of return on private investment, as suggested by the U.S. Office of Management and Budget.
Incorporated risk management into their strategic plan : Based upon your professional experience or a recent event, provide an example of how an organization successfully or unsuccessfully incorporated risk
The price per share of the stock and shareholder wealth : Evaluate the two alternatives in terms of the effect on the price per share of the stock and shareholder wealth.
Define the difference between an ordinary annuity : Define the difference between an ordinary annuity, an annuity due and a perpetuity. Give an example of each. Discuss the calculated difference
Weighted average cost of capital after second breakpoint : NCC Corporation is considering building a new facility in Texas. What is the Weighted Average Cost of Capital (WACC) after the second breakpoint?

Reviews

Write a Review

Financial Management Questions & Answers

  What is the firm cost of debt

A firm has a weighted average cost of capital of 9.6 percent and a cost of equity of 14.5 percent. What is the firm's cost of debt?

  Considering an investment with the cash flows

You are considering an investment with the following cash flows. If the required rate of return for this investment is 13.5%, should you accept it based solely on the internal rate of return rule? Why or why not?

  Construct a contingency graph for a short straddle

Currency option contingency graphs.  The current spot rate of the Singapore dollar (S$) is £0.34. Construct a contingency graph for a short straddle using these options.

  What is the present value of the annuity

What is the present value of the following annuity? $1,931 every half year at the beginning of the period for the next 12 years,

  Bonds is equal to the stated rate on the bond contract

The coupon rate or required return of bonds is equal tothe stated rate on the bond’s contract.

  Does cmos have an unrealized gain or loss on the derivative

Does CMOS have an unrealized gain or loss on the derivative for the period? On the bonds? Will earnings increase or decrease due to the hedging arrangement? Why?

  Biotechnology startup looking to develop plan to expand

Your client is a biotechnology startup looking to develop a plan to expand their operations.

  Exact expected real risk premiums on the portfolio

If your portfolio is invested 35 percent each in A and B and 30 percent in C, what is the portfolio expected return? What is the standard deviation? What are the approximate and exact expected real risk premiums on the portfolio?

  Depreciation deduction and unrecovered investment

Electric generating and transmission equipment is placed in service at a cost of $3,100,000. It is expected to last 30 years with a salvage value of $250,000. What is the MACRS-GDS property class? Determine the depreciation deduction and the unrecove..

  Operating cash flow and value of the property

Consider a commercial property that costs $1 million (90% building, 10% land) with the CAP rate of 10%. Assume that the operating cash flow and value of the property both grow at a rate of 5% per year. Suppose 80% of the property value is financed wi..

  Sample from the same population

Suppose a researcher collected data with n = 200 and came up with a sample mean of 83 and 95% confidence interval [78, 88]. If the researcher collected another sample from the same population with n = 200,

  What is enterprise value-EBITDA multiple for this company

The market value of the equity of Thompson, Inc., is $590,000. The balance sheet shows $36,000 in cash and $193,000 in debt, while the income statement has EBIT of $92,000 and a total of $137,000 in depreciation and amortization. What is the enterpri..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd