Calculate the percentage error using the abc costs

Assignment Help Managerial Accounting
Reference no: EM13949389

Airepart, Inc., produces two different types of subassemblies for the aircraft industry. Airepart produces a major component for the subassemblies in the cutting and welding department. Other parts and the manufactured component are then assembled in the assembly department. The activities, expected costs, and drivers associ- ated with these two manufacturing processes are as follows:

Process

Activity

Cost

Activity Driver

Expected Quantity

Cutting and

Welding

$ 2,000,000

Welding hours

4,000

Welding

Machining

1,000,000

Machine hours

10,000

 

Inspecting

Materials handling

70,000

52,000

No. of inspections

No. of moves

1,000

12,000

 

Setups

     400,000

No. of batches

100

 

 

$3,522,000

 

 

Assembly

Changeover

$ 28,000

Changeover hours

1,000

 

Rework

50,000

Rework orders

50

 

Testing

40,000

No. of tests

750

 

Materials

handling Engineering support

60,000

       70,000

No. of parts

Engineering hours

50,000

2,000

 

 

$ 248,000

 

 

Note: In the assembly process, the materials handling activity is a function of product characteristics rather than batch activity.

Other overhead activities, their costs, and drivers are as follows:

Activity Cost Activity Driver Quantity

Purchasing

$50,000

Purchase  requisitions

500

Receiving

70,000

Receiving orders

2,000

Paying suppliers

80,000

No. of invoices

1,000

Providing space and utilities

    30,000

Machine hours

10,000

 

$230,000

 

 

Other production information concerning the two subassemblies is also provided as follows:

  Subassembly A Subassembly B

Units produced

1,500

3,000

Welding hours

1,600

2,400

Machine hours

3,000

7,000

Inspections

500

500

Moves

7,200

4,800

Batches

45

55

Changeover hours

540

460

Rework orders

5

45

Tests

500

250

Parts

40,000

10,000

Engineering hours

1,500

500

Requisitions

425

75

Receiving orders

1,800

200

Invoices

650

350

The per-unit overhead costs using the 14 activity-based drivers are $1,108 and $779 for Subassemblies A and B, respectively.

Required

1. Determine the percentage of total costs represented by the three most expensive activities.

2. Allocate the costs of all other activities to the three activities identified in Requirement 1. Allocate the other activity costs to the three activities in proportion to their individual activity costs. Now assign these total costs to the products using the drivers of the three chosen activities.

3. Using the costs assigned in Requirement 1, calculate the percentage error using the ABC costs as a benchmark. Comment on the value and advantages of this ABC simplification.

Reference no: EM13949389

Questions Cloud

Used as the annual sales figure when evaluating this project : Travel America Coaches currently sells 15,000 motor homes per year at $94,000 each, and 1,500 luxury motor coaches per year at $159,000 each. The company wants to introduce a low-range camper to fill out its product line; it hopes to sell 3,000 of th..
Are these intervals more useful for planning your expansion : Run a regression of sales against local income (only). Based on this regression, give an interval that you are 95% confident will contain your sales in a neighborhood with total income $200M. Do you think this regression is useful for planning you..
What is the amount of kristi realized gain : What is the amount of Kristi's realized gain and recognized gain and the basis in her new property?
What is the wacc it should use for the project : Lawler's is considering a new project. The company has a debt-equity ratio of 0.62. The company's cost of equity is 15.1 percent, and the aftertax cost of debt is 8.8 percent. The firm feels that the project is riskier than the company as a whole and..
Calculate the percentage error using the abc costs : Using the costs assigned in Requirement 1, calculate the percentage error using the ABC costs as a benchmark. Comment on the value and advantages of this ABC simplification.
How many pounds of plastic does aja need to purchase in 2016 : The Aja Co. expects to produce 2,000 baskets in 2016. Each basket requires 2 pounds of plastic. Aja has 225 pounds of plastic on hand at the end of 2015, and it wants to have 190 pounds on hand at the end of 2016. How many pounds of plastic does Aja ..
Can terrence enforce the contract : Terrence, an adult, enter into a contract with Bobby, a 16 year old. Before either party changes position, Bobbys parents find out and tell Terrence the deal is off. Can Terrence enforce the contract
Why capm equation might be more relevant than other : Explain with a graph how SML is different from CML. Why CAPM equation might be more relevant than other equations when calculating required rate of return.
Assume spending will continue at the same rate : Your project is progressing well in your estimation. Your team has collected the following data. From these data, calculate the project’s ETC. Activity A is 60% complete at a cost so far of $50,000. It was estimated to cost $200,000 when finished. It..

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd