Calculate the per day costs for crashing each activity

Assignment Help Project Management
Reference no: EM131841294

Question: You are considering the decision of whether or not to crash your project. After asking your operations manager to conduct an analysis, you have determined the "precrash" and "postcrash" activity durations and costs, shown in the following table (assume all activities are on the critical path):

109_ASC.png

a. Calculate the per day costs for crashing each activity.

b. Which are the most attractive candidates for crashing? Why?

Reference no: EM131841294

Questions Cloud

Developing in the nile river and the yellow river : How do you compare the civilizations developing in the Nile River and the Yellow River. Cite your sources.
What is the big-oh running time of the given algorithm : Describe an O(n log(n)) algorithm for checking. What is the big-Oh running time of the following algorithm to find an element in an n × n array?
Describe the initial framework for balanced scorecards : How balanced scorecards are used, their limitations, their positive potential for an organization, and so forth.
Reading questions for things fall apart by achebe : Okonkwo was very concerned to project an image of strength and masculinity. What did he do to prove his manhood? Give at least two examples.
Calculate the per day costs for crashing each activity : You are considering the decision of whether or not to crash your project. After asking your operations manager to conduct an analysis, you have determined.
Determine sally cost recovery for the building : The gross rents from the businesses are $60,000 and the gross rents from the apartments are $310,000. Determine Sally's cost recovery for the building
Discussion of an application of commercial thinking : Bring an example to discussion of an application of commercial thinking from the time period of 1501AD to 1600. Explain the event, the time
What region had the greatest empires at the time : What region had the greatest empires at the time between 600 BCE and 200 BCE? Why would you argue for that region? Cite your sources.
How many days would you advise that the project be crashed : Suppose direct costs of crashing the project only increased $5,000 per day crashed at a steady rate (starting with $125,000 on day 60).

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd