Question: You are now in week 10. After the analysis done in week 8, the new data collected now find that the progress of 'build' is 65% in week 9 and increase to 75% in week 10. The next phase of installation has not started. The project spent another RM5000 at week 9 and RM6000 at week 10 for the 'build' phase. Now calculate the new earned value in week 10. Using CPI and CV, compare performance at week 10 with week 8. Calculate the new FCAC and TCPI. Explain.
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd