CAPITAL BUDGETING

The three projects identified below should be used to answer the next 4 questions.  Each project represents an investment opportunity to an organization.  The relevant rate of interest, called the cost of capital, is 3.5%.

 

                                    PROJECT A                 PROJECT B                 PROJECT C

            CF0                 -$20,000                     -$15,000                     -$50,000

            CF1                   $  4,500                      $      500                     $  6,000

            CF2                   $  4,000                      $      500                     $  6,000                   

            CF3                   $  3,500                      $      750                     $  6,000

            CF4                   $  3,000                      $   1,000                     $  6,000

            CF5                   $  2,500                      $   1,500                     $  6,000

            CF6                   $  2,000                      $   2,000                     $  6,000

            CF7                   $  1,500                      $   2,500                     $  6,000

            CF8                   $  1,000                      $   3,000                     $  6,000

            CF9                   $      750                     $   3,500                     $  6,000

            CF10                 $      250                     $   4,000                     $  6,000

 

1.         What are the returns on investments for each project?  You will need to calculate the internal rates of return.

 

            1a.       A.         3.31% - 3.40%

                        B.         3.41% - 3.50%

                        C.         3.51% - 3.60%

                        D.         3.61% - 3.70%

                        E.         3.71% - 3.80%

                        F.         None of the above.

 

            1b.       A.         3.31% - 3.40%

                        B.         3.41% - 3.50%

                        C.         3.51% - 3.60%

                        D.         3.61% - 3.70%

                        E.         3.71% - 3.80%

 

            1c.       A.         3.31% - 3.40%

                        B.         3.41% - 3.50%

                        C.         3.51% - 3.60%

                        D.         3.61% - 3.70%

                        E.         3.71% - 3.80%

                        F.         None of the above.

 

2.         Calculate the net present values for each project.

 

            2a.       A.         ($219) - ($120)

                        B.         ($119) - ($20)

                        C.         ($19) - $80

                        D.         $81 - $180

                        E.         $181 - $280

                        F.         None of the above.

 

            2b.       A.         ($219) - ($120)

                        B.         ($119) - ($20)

                        C.         ($19) - $80

                        D.         $81 - $180

                        E.         $181 - $280

                        F.         None of the above.

 

            2c.       A.         ($219) - ($120)

                        B.         ($119) - ($20)

                        C.         ($19) - $80

                        D.         $81 - $180

                        E.         $181 - $280

                        F.         None of the above.

 

3.         Your boss has told you that she believes Project B is the best because it has the greatest summed positive cash flow (i.e., $19,250) relative to its initial cost (($19,250 -$15,000) / 15,000 = 28%).  She believes the next best is Project C, with a net positive     cash flow to cost of 20% (($60,000 - $50,000) / $50,000);  Project A is the least favorable at 15%. 

 

            3a.       Is there a flaw in her thinking?

                        A.         No, her finding is consistent with the time value of money analysis.

                        B.         No, her methodology is valid along with the time value of money.

                        C.         Yes, her methodology is not a part of a valid TVM analysis.

                        D.         Yes, she should use (total positive flows / cost).

                        E.         None of the above.

 

            3b.       If so, how should the projects be ranked in terms of favorability?

                        A.         A is best, then B, with C being worst.

                        B.         B is best, then C, with A being worst.

                        C.         C is best, then A, with B being worst.

                        D.         A is best, then C, with B being worst.

                        E.         None of the above.

 

4.         What happens if the cost of capital, due to a worsening economy, drops to 2.5%? Does the profitability order of the projects change?

            A.         Yes: order should now be A, B, C.

            B.         Yes: order should now be B, C, A.  

            C.         Yes: order should now be C, B, A.  

            D.         Yes: order should now be A, C, B.  

            E.         No.

 

5.         Consider cash flows that have multiple periods per year.  Option 1 has quarterly periods and Option 2 has semi-annual periods.  If you invest $10,000 today in each option and each option pays out $2,800 total per year, what are the following values given a required annual rate of 5%?

 

            5a.       IRR of Option 1

                        A.         1.00% - 1.99%

                        B.         2.00% - 2.99%

                        C.         3.00% - 3.99%

                        D.         4.00% - 4.99%

                        E.         5.00% - 5.99%

                        F.         None of the above.

 

            5b.       IRR of Option 2

                        A.         1.00% - 1.99%

                        B.         2.00% - 2.99%

                        C.         3.00% - 3.99%

                        D.         4.00% - 4.99%

                        E.         5.00% - 5.99%

                        F.         None of the above.

 

            5c.       NPV of Option 1

                        A.         $0 - $24

                        B.         $25 - $49

                        C.         $50 - $74

                        D.         $75 - $99

                        E.         $100 - $124

                        F.         None of the above.

 

            5d.       NPV of Option 2

                        A.         $0 - $24

                        B.         $25 - $49

                        C.         $50 - $74

                        D.         $75 - $99

                        E.         $100 - $124

                        F.         None of the above.

 

            5e.       Would it preferable to receive daily payments rather than quarterly or semi-annually?

                        A.         Daily is preferred

                        B.         Semi-annually is preferred

                        C.         Monthly is preferred

                        D.         Quarterly is preferred

                        E.         Annually is preferred

Reference no: EM13492949

Questions Cloud

How far does it roll back up the ramp : A 500 g cart is released from rest 1.00 m from the bottom of a frictionless, 30.0 degree ramp. how far does it roll back up the ramp
What is their speed at the bottom of the slope : The skiing duo of Brian (83 ) and Ashley (46 ) is always a crowd pleaser. In one routine, Brian, wearing wood skis, starts at the top of a 280 long, What is their speed at the bottom of the slope
Identifying all adjustments and accrued expenses : Identifying all adjustments and Accrued Expenses/Prepaid Expenses Other entries
Define how many moles of hydrazine are produced of ammonia : ammonia, NH3, reacts with hypochlorite ion, OCl-, to produce hydrazine, N2H4. How many moles of hydrazine are produced from 5.85 mol of ammonia if the reaction has a 78.2% yield
Calculate the net present values for each project : The three projects identified below should be used to answer the next 4 questions.  Each project represents an investment opportunity to an organization.  The relevant rate of interest, called the cost of capital, is 3.5%.
How to calculate the normal boiling point of the liquid : A certain liquid has a vapor pressure of 92.0 Torr at 23.0 °C and 204.0 Torr at 45.0 °C. Calculate the normal boiling point of this liquid.
Define how much heat energy is needed to raise temperature : The specific heat of a certain type of cooking oil is 1.75 J/(g·°C). How much heat energy is needed to raise the temperature of 2.02 kg of this oil from 23 °C to 191 °C
Prepare the journal entry to record the acquisition : Using Excel, prepare the journal entry to record the acquisition by Bullseye Company.
Estimate the magnetic field at the nucleus : In the Bohr-model hydrogen atom the single electron orbits the nucleus in a circle of radius a= 5.3*10 (-11) making f= 6.6*10( 15) revolutions each second

Reviews

Write a Review

Financial Accounting Questions & Answers

  Prepare income statement and a retained earnings statement

Prepare an adjusted trial balance and prepare the income statement and a retained earnings statement for July and a classifiedbalance sheet at July 31.

  Illustrate what is the company total tax liability

Illustrate what is the company's total tax liability to both jurisdictions for each of the two alternative transfer pricing scenarios?

  Compare tax consequences to the shareholder

Compare the tax consequences to the shareholder and the distributing corporation of the following three kinds of corporate distributions: ordinary dividends, stock redemptions, and complete liquidations.

  Calculate internal rate of return of the investment

Determine the net present value of the investment in the service center. Should Munster invest in the service center? Calculate internal rate of return of the investment to the nearest ½ percent.

  Find out the liability for this loan

Both held-to-maturity debt securities and available-for-sale debt securities must be reported at their fair market value at year-end.

  What consolidation entry could be needed for these bonds

What consolidation entry could be needed for these bonds on December 31, 2012?

  Compute amount of wiley net income for the month

Wiley Company had total revenues of $300,000 for a recent month. During the month the company incurred operating expenses of $205,000 and purchased land for $45,000. Compute amount of Wiley's net income for the month.

  Question sea eagles inc uses weighted-average process

question sea eagles inc. uses weighted-average process costing. during the current period 60000 units were started

  Evaluate current variable cost per skier

Consider that SnowCastles has found ways to cut its fixed costs to $31 million. Evaluates its new target variable cost per skier/snowboarder? Compare this to the present variable cost per skier-snowboarder.

  Prepare a schedule showing the income statement

Prepare a schedule showing the income statement effects for the year ended 31st December, 2012 as a result of the above facts.

  Illustrate what is the amount of cash flows from operations

A company's cash flow on total assets ratio equals 16%. If average total assets equal $2,937,500 and total cash flows equal $600,000, illustrate what is the amount of cash flows from operations?

  What data may be considered as fraud risk factors

What data may be considered as fraud risk factors

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd