Calculate the minimum stopping sight distance

Assignment Help Civil Engineering
Reference no: EM132369730

Pasture Road Project - Assignment Brief

Introduction and Background

Bordertown is a rural town servicing a diverse and vibrant farming and grazing industry. The main agricultural supply, produce / livestock distribution and industrial areas are located on the northern side of town. The majority of heavy vehicle traffic travels to and from the north-west and accesses Bordertown via the Main Highway. Unfortunately this means that heavy vehicles, including B-double trucks, are required to pass through the centre of town (CBD) causing traffic congestion and safety issues.

There is an alternate route via Pasture and North roads. However, Pasture Road is currently narrow, mostly single lane seal and posted at 60km/h - it is not a desirable route particularly for heavy vehicles. Refer Figure 1-1.

The road authority now wishes to upgrade Pasture Road to make it a viable alternate route, particularly for heavy Commercial Vehicles (CVs). Pasture Road is currently 19m Semi general access only, however it is to be upgraded to a B-Double route.

486_Location Diagram.jpg

Figure 1-1 Location Diagram

2.0 Project Site

Pasture Road is in a rural environment. Terrain is mostly open and flat to mildly undulating. Land use adjacent to the road in the vicinity of project site is predominantly pastural / grazing.
Pasture Road has been split into 3 sections (refer Figure 1-2) and is to be designed and constructed as funding becomes available.
• Section 1 (≈5km) to be designed by others (not part of this project)
• Section 2 (≈2.7km) being designed by your team (this project/assignment)
• Section 3 (≈3.8km) to be designed by others (not part of this project)

342_Sections.jpg

Figure 1-2 Sections

3.0 Existing Road (Pasture Road)
With reference to Figure 1-2.

Section 1
• Approximately 5 km long and reasonably straight. There are several short length horizontal curves ranging 700 to 750m in radius.
• This section is single lane seal with gravel shoulders.
• Terrain is mildly undulating.
• Future upgrade:
o Will mostly keep the existing alignment,
o Cross section will be based on that developed for Section 2.

Section 2
• Approximately 2.7 km long and has three horizontal curves ranging 325 to 450m in radius.
• Existing cross section (variable):
o 7.6m carriageway
» 2x 2.8m sealed traffic lanes
» 2x 1.0m unsealed shoulders
o Crossfall is 2-4%
o Batters (cut, fill and table drain) are generally 3:1 but sometimes 2:1
o Table drains are V-drains

Section 3
• Approximately 4.2 km long and is generally straight. There are two horizontal curves, R500 and R680 respectively.
• This section is single lane seal with gravel shoulders.
• Terrain is reasonably flat
• Future upgrade:
o Will mostly keep the existing alignment,
o Cross section will be based on that developed for Section 2.

4.0 Traffic Prediction
Current traffic along Pasture Road is very low and largely consists of local farming traffic with occasional livestock semi-trailers.
For the purposes of design, the road authority commissioned a traffic modelling study (including an origin-destination survey) to predict the expected traffic volume and composition at opening of the upgraded road once fully upgraded (all three sections).
The findings of the modelling are:
• AADT: 730 vehicles
• Percentage of commercial vehicles (%CVs) = 30%
• Growth rate for traffic (from year opening onwards) will be 2.2 - 3.5% Pasture Road will be sign posted as the primary route for CVs accessing Bordertown.

5.0 Design Requirements
The following design requirements and intentions have been set by the road authority.
• Design guideline - Guide to Road Design by Austroads (AGRD).
• Following existing alignment is preferable, however it is expected that some realignment will be required in the vicinity of Dry Creek (which is within Section 2) to facilitate the construction of a new replacement structure.
• Maximum superelevation to be used is 6%.
• Pasture Road is not considered a bus or cycling route.
• Posted speed of road to be increased to 90km/hr.
• Design life = 30 years.
• Traffic:
• AADT growth rate 3% per year (compound growth).
• Design Vehicle to be B-Double.
• Drainage:
• Dry Creek Bridge (timber):
o Currently floods (overtops) and is to be replaced with a large box culvert structure to improve flood immunity - flood water is not to inundate the traffic lanes for design flood (AEP 2%).

o The replacement culvert has been designed by hydraulic specialists - it is to be 4/2400mm x 2400mm RCBC.
• Existing table drains show signs of scour. Erosion needs to be mitigated.
• Intersections:
• Traffic analysis warrants basic intersection layouts for left and right turns into minor roads.
• Intersection safety is an important consideration.

6.0 Road Design Project Tasks (Assignment 1)

Scope of Assignment Work
You are required to work in teams of 4. Approach is collective and collaborative learning. Tasks should be equally divided amongst team members.
Work should be aligned with the material presented during lectures. Sections of AGRD not referenced during lectures do not need to be used.

Tasks
Your team is assisting the preliminary or feasibility design (based on information provided in Sections 1 to 5 above) of the project:
• A series of tasks aligned to lecture material will be issued (generally on a weekly basis). The outcome of these tasks is to be reported in your Design Report (refer Section 6.3).
o Some of the tasks will be design based where your team is to propose a design solution for consideration.
o Other tasks will be to review work by others and to either verify if proposal is satisfactory or, suggest changes / improvements.
• Reporting in Design Report is to include your thinking / rationale for proposal. You also need to explain / justify selection of relevant criteria.
This project is informed by:
• The Guide to Road Design (AGRD) and Guide to Traffic Management
(AGTM) by Austroads.
Furthermore:
• Pavement design is not part of this assignment / not to be included.
• Private accesses are not part of this project.

Deliverables
Consistent with this brief your team shall specifically deliver for Assignment 1, the following:

1. Design Report (8 pages of main body text (Sections 1 to 9)) must be completed using the provided template. Any work presented beyond page 8 will not contribute to overall mark. Changes to structure of report will be penalised in marking of assignment.
• Target audience for report are experienced road design engineers.

• Appendices are additional material to main body of report and must contain appropriate detail, calculations and drawings sufficient to inform report audience and support your findings. Appendices must be correctly referenced from within the body of the report. If they are not referenced, they will not be considered in the marking of assignment.

2. Minimum formatting for report: text no less than 11pts, paragraph spacing no less than - Before = 0pts / After = 6pts and Line spacing no less than 14pts.

7.0 Timing

Lectures will be progressively delivered covering material essential for undertaking and completing the assignment:
• Assignment 1: Is due to be submitted by 11:59pm, Friday 13 September 2019.

Relationship of this Project to Unit EGH472

This project aligns with unit learning outcomes:

1. Application of theoretical knowledge, design methodologies, and codes of practice correctly in the design (review) of a road.
2. Use of informational sciences to investigate, analyse and synthesise the civil engineering systems in place along a corridor for which a road is to be designed.
3. Awareness of the social and economic contexts and sustainable engineering practice in the design of a road.
4. Correct written literacy and appropriate collaborative strategies in the preparation of road design submission.

The project, to be completed in teams of four contributing equally, will be the design of key element a segment of road in a rural setting. The purpose of the facilitated design is to give you up-to-date exposure to near real-life road infrastructure projects and to encourage you to discuss the methods and steps of the design process with your peers (i.e. your team).

It is important to point out that the project is a simulated one, and as such, does not correspond directly with the extent of work required, timelines, or organisational arrangements of a real project. Rather, it extracts certain key exercises that would be carried out by the various actors within the road design process.

Assignment Task 1

1. Key information
The Assignment Brief provides all relevant information and guidance with respect to the intentions / requirements of the client (road authority).
Tasks set within this document provide additional guidance and information (details) to complete required work for submission as Assignment 1.

2. Linkage between Lectures and Assignment
Lectures completed and related to tasks:
• L1 - Design Approach and Speed
• L2 - Cross Section Design and Safety Related Design Report sections:
• 1 - Introduction
• 2 - Design traffic
• 3 - Design Speed
• 4 - Type Cross Section

3. Tasks
Commence authoring Section 1 of Design Report.
• All information has been provided however you can continue to refine this section over next few weeks.

Commence and complete authoring of Section 2 of Design Report.
• All information has been provided. It is essential to complete this section as it informs your design tasks.

Commence and complete authoring of Section 3 of Design Report.
• All information has been provided. Careful assessment and consideration is required. It is essential to complete this section as it informs your design tasks.

Commence and complete authoring of Section 4 of Design Report.
• All information has been provided. You are required to develop / design the type cross section (or sections) for the project. For the report, it is suggested to present the elements of the type cross section(s) in tabulated form. You are also required to produce a drawn version of your designed type cross section(s). Table and rationale should be within main body of report, but drawings should be placed in an appendix.

Assignment Task 2

1. Key information
The Assignment Brief provides all relevant information and guidance with respect to the intentions / requirements of the client (road authority).
Tasks set within this document provide additional guidance and information (details) to complete required work for submission as Assignment 1.

2. Linkage between Lectures and Assignment
Lectures completed and related to tasks:
• L3 - Horizontal
Related Design Report sections:
• 6.1 - Horizontal Alignment.

3. Tasks
3.1. Commence and complete authoring of Section 6.1 of Design Report.
• All information has been provided.
• You are required to fully design the first curve currently shown/proposed as R325 (refer Appendix 1). This radius approximately matches the existing curve and it is desired to keep this radius as it maximises the use of existing asset. However you are able to decrease/increase the radius of curve.
• Refer Appendix 2 for geometric detail of example curves at this location.
• You are required to fully design the combined second and third curves currently shown/proposed as R450 reverse curves (refer Appendix 3). You are able to decrease/increase the radius of curve.
• Refer Appendix 4 for geometric detail of example curves at this location.
• Dry Creek crosses new alignment, between the above reverse curves, at approximately Ch1480 (refer Appendix 3).
• Larger drawings / diagrams, such as superelevation diagrams, should be placed in an appendix.

Assignment Task 3
1. Key information
The Assignment Brief provides all relevant information and guidance with respect to the intentions / requirements of the client (road authority).
Tasks set within this document provide additional guidance and information (details) to complete required work for submission as Assignment 1.

2. Linkage between Lectures and Assignment
Lectures completed and related to tasks:
• L4 - Sight Distance and Vertical Alignment Related Design Report sections:
• 5 - Sight Distance
• 6.2 - Vertical Alignment.

3. Tasks
Commence and complete authoring of Section 5 of Design Report.
• All information has been provided.
• Using your design speed, calculate the minimum Stopping Sight Distance to be used for this project in these situations:
o flat
o 6.50% downhill
o 4.25% uphill.
• Calculate the curve perception sight distance (if required) to be used to assess the following possible horizontal curve radii for the project:
o R350 ; transitioned, Lp = 60m
o R500 ; un-transitioned, use 80m of arc
Commence and complete authoring of Section 6.2 of Design Report.
• All information has been provided.
• Using your design speed, calculate the minimum Crest and Sag vertical curves to be used for this project.

Assignment Task 4

1. Key information
The Assignment Brief provides all relevant information and guidance with respect to the intentions / requirements of the client (road authority).
Tasks set within this document provide additional guidance and information (details) to complete required work for submission as Assignment 1.

2. Linkage between Lectures and Assignment
Lectures completed and related to tasks:
• L5 - Alignment Coordination Related Design Report sections:
• 6.3 - Alignment Coordination.

3. Tasks
3.1. Commence and complete authoring of Section 6.3 of Design Report.
• All information has been provided.
• Assess the four attached drawings for alignment coordination.
• Determine if the coordination is acceptable or not and provide a brief commentary within the report on each drawing.
• If you identify any issues, provide a suggested improvement.

Assignment Task 5

1. Key information
The Assignment Brief provides all relevant information and guidance with respect to the intentions / requirements of the client (road authority).
Tasks set within this document provide additional guidance and information (details) to complete required work for submission as Assignment 1.

2. Linkage between Lectures and Assignment
Lectures completed and related to tasks:
• L6 - Drainage & Intersections Related Design Report sections:
• 7 - Road Drainage
• 8 - Intersections
• 9 - Conclusions and Recommendations
3. Tasks - Drainage
Commence and complete authoring of Section 7 of Design Report.
• All information has been provided.

Table Drain Assessment
Between Chainages 35 - 400 there will be a table drain. Check the capacity of the drain and velocity of flow and assess if design is satisfactory or not?

Table drain geometry @ Ch. 35:

407_figure1.jpg


• Average grade of road over length of table drain = 4.1%
• Maximum permissible velocity is 2.0m/s
• Hydrology calculates the inflow to drain as 0.065m3/s per 10m (of table drain)
• If not suitable, suggest how to improve.

Between Chainages 1850 - 2050 there will be a table drain. Check the capacity of the drain and velocity of flow and assess if design is satisfactory or not?

Table drain geometry @ Ch. 1850:

2271_figure2.jpg

• Average grade of road over length of table drain = 5.5%
• Manning's is slightly better, n = 0.04
• Maximum permissible velocity is 2.0m/s
• Hydrology calculates the inflow to drain as 0.065m3/s per 10m (of table drain)
• If not suitable, suggest how to improve.

Bridge Replacement Culvert Assessment
The 4/2400x2400RCBC culvert as shown in Appendix 1 (2 drawings) has been designed by others. Undertake a simple assessment of the design (identify any adverse issues) and provide comment on suitability.

4. Tasks - Intersections
4.1. Commence and complete authoring of Section 8 of Design Report.
• All information has been provided.
• Calculate the required SISD for the 3 intersections drawings in Appendix 2.
• Assess the intersections for location suitably:
o Assessment to be based on original design as provided; not modifications you may have made to the alignment.
o You will need to consider the vertical alignment as previously supplied.
o There are no trees, buildings or other objects located close to the road that would impede visibility.
• If you identify any issues, provide a suggested improvement.

5. Tasks - Finalise
Commence and complete authoring of Section 9 of Design Report.

Design Report finalisation.
• Review and finalise / complete all sections of report.
• Submit report by due date.

Attachment:- Pasture Road Project.rar

Reference no: EM132369730

Questions Cloud

Explain what are the issue of securing backups : Discuss the issue of securing backups. There have been several incidents lately in which backup media containing personal customer information were lost.
What sort of attacks might take place : You are the web master for the Republican Party National Committee. Prepare a risk assessment analysis for your website. Some questions to consider.
Corporate social responsibility and financial performance : Analyze the organization's performance in these dimensions: environmental sustainability, corporate social responsibility, and financial performance.
Define compliance issues that the company may encounter : ISOL533 - Using your reading in Chapter 4 as a guide and the threats that were listed in the Project Overview, write a 2 - 3 page paper that addresses.
Calculate the minimum stopping sight distance : EGH472 - Advanced Highway and Pavement Engineering - Queensland University of Technology - Determine if the coordination is acceptable or not and provide
Define risk and costs of compromised data integrity breaches : In 500 words or more, discuss the risk and costs of compromised data integrity breaches. Focus on integrity not confidentiality. Look at military, education.
Describe an issue of globalization in brief : Choose an issue within the topic of globalization that interests you and fits within your PhDIT concentration or research area of interest.
Discuss differences between managing change-leading change : Discuss the differences between managing change and leading change. What are the advantages of being a change leader?
What are the key issues in resourcing innovation process : What are the key issues in resourcing this innovation process? Your response should be 250-300 words. Respond to one posting provided by your classmates.

Reviews

Write a Review

Civil Engineering Questions & Answers

  Determine the smallest yield stress for a steel

The state of stress acting at a critical point on the seat frame of an automobile during a crash is shown in the figure. Determine the smallest yield stress for a steel that can be selected for the member, based on the maximum-shear-stress theory.

  Determine the moment capacity mu for a rectangular beam

Determine the moment capacity, Mu, for a rectangular beam that has b=24in, h=14in, d=11.5in, d’=2.5in, f’c=4ksi, fy=60ksi, As’=2#10, As=3#10 and 2#11 if:

  What roughness coefficient would be required to produce

Evaporation rate in a 3650 acre-lake is 100 acre-ft/d. If inflow to the lake is 25.2 cfs, determine the change in storage (ft) during 365 days.

  Obtain the dimensionless groups that charactrize the problem

The power loss, p , in a journal bearing depends on length, L; diameter, D; clearance, c; and rotational speed, w. You also have to worry about lubricant viscosity, density, and pressure. Obtain the dimensionless groups that charactrize this probl..

  What is the elevation of lower point

A pre- engineering base line was run down a very steep hill.rather than measure horizontaily down hill with steel tape: surveyor measured the vertical angle with the theodolite and slope distance with 16m steel tape.

  Plot the three values on the same diagram and comment on the

A wave has a height of 1.5 m in water 5 m deep and a wave period of 6 s. Plot the horizontal component of velocity, the vertical component of acceleration, and the dynamic pressure at a point 2 m below the still water level versus time for a 6-s inte..

  Determine the average value of k in meter per sec

A stopwatch was started when h was 501 mm and read 17.6 seconds when h was 244 mm; the test was repeated for a drop from 254 mm to 97 mm and the time was 22.4 seconds.

  Survey with construction applicationsquestion 1layout of

survey with construction applicationsquestion 1layout of highway curvesa. is an approximation technique.b. should be

  Determine maximum dry density

A series of Standard Proctor compaction tests was performed on a soil with a specific gravity of 2.68 with the following results: Determine: Maximum dry density; Optimum moisture content

  Maximum shearing stress and corresponding normal stress

For the state of plane stress shown,determine a)principal planes b)principal stresses c) maximum shearing stress and corresponding normal stress

  Consider the function to determine its root

The following function is used to determine a parachute’s falling velocity. Consider the function to determine its root, the drag coefficient, c such that the velocity, v is 40 m/s after a free-falling time (t) of 10 second. f(c)=(gm/c)(1-e^(-(c/m)t)..

  Find additional force that will be require to maintain speed

A passenger car being driven on a flat and straight section of a highway at a speed of 65 mph reaches a curved section of the highway with a grade of 5% and a radius of 1,500ft.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd