Calculate the minimum cycle time

Assignment Help Operation Management
Reference no: EM13104195

Six tasks, with times and precedence requirements as shown in the following table, are to be assigned to workstations. The desired output is 160 units per 8 hour day.
Task times and precedence relations are as follows.
Task time (minutes) preceeds task
A 1.2 B
B 0.9 C
C 1.5 D
D 0.4 --
E 1.9 B
F 1.6 B
A. What is the minimum cycle time? What is the maximum c ycle time? What is the calculated cycle time?
B. What is the minimum number of stations needed? Show work on scanned sheet.
C. Assign tasks to workstations based on greatest number of following tasks. Use longest processing time as tie-breaker. If ties still exist, assume indifference in choice.
D. Compute the percentage idle time for the assignment in part c.

Reference no: EM13104195

Questions Cloud

Probability related to division of housework : Is the proportion of men who felt that division of housework was fair greater than the proportion of women who felt the division of housework was fair? Use alpha = .05 for the test.
Estimate the process capability index for vaxidene : Crawford Pharmaceuticals has developed a new drug, Vaxidene, which is administered in the form of a pill. The target amount for a single dose is 100 mg.
How trip to ocean can be relaxing escape to faraway places : What sentence is topic sentence of paragraph? What sentence is unrelated to topic and can be eliminated? Trip to ocean can be relaxing escape to faraway places.
Scheduled mean completion time : An automobile assembly line operation has a scheduled mean completion time of 2.2 minutes. Because of the effect of completion time on both preceding and subsequent assembly operations, it is important to maintain the 2.2 minute mean completion ti..
Calculate the minimum cycle time : Six tasks, with times and precedence requirements as shown in the following table, are to be assigned to workstations. The desired output is 160 units per 8 hour day.
Estimating breakeven in dollars : GX Corporation is developing a new innovative product. To launch the product, fixed costs are set at $140,000. Variable Costs are set at $75. They desire to break even by selling 1,000 units.
Regression model possible using the set of variables : Develop the "best" regression model possible using this set of variables to help you predict the Risk. State your final model. Interpret the coefficients for the model (i.e. what do the numbers mean?).
Computing probability from using mean : Brake Pads- A brake pad manufacturer claims its brake pads will last for 38,000 miles. You work for a consumer protection agency and you are testing this manufacturer's brake pads.
Information about calculating the probability : An instructor has a test bank consisting of 300 easy true-false questions, 200 difficult true-false questions, 500 easy multiple choice questions and 400 difficult multiple choice questions.

Reviews

Write a Review

Operation Management Questions & Answers

  What profit earned from the sale of each large poster

Student Enterprises sells 2 sizes of wall posters, a large 3- by 4-foot poster and a smaller 2- by 3-foot poster. The profit earned from the sale of each large poster.

  Illustrate what are the pros also cons of this idea

Examine design-depend increment alism, which is frequent product redesign throughout the product's life. Illustrate what are the pros also cons of this idea

  Discuss the positive aspects of globalization

Discuss the positive aspects of globalization and contrast these with the negative aspects of globalization from the perspective of a small business

  A company is considering a new venture

A company is considering a new venture. This venture will require the purchase of $550,000 of equipment (which will be depreciated straight-line to zero over the life of the project and will have no salvage value)

  Commercialization of the evista product

Is the "heavyweight" project teams an approach that you would recommend to Lilly for commercialization of the Evista product

  Draw an aon diagram of the project including activity

a Draw an AON diagram of the project including activity durations and define the critical path, lisitng all critical activities in chronological order

  Linear programming-maximize planting

A farmer in Lowa owns 45 acres of land. He is going to plant each acre with wheat or corn. It clearly indicates how the derived value has been reached.

  Compute forecasts for the remaining five months

Compute forecasts for the remaining five months utilizing simple exponential smoothing. Which of the changes being considered by the manager of XYZ contradict the lean philosophy.

  Discuss how supply and demand would be affected

Discuss how supply and demand would be affected under each of the four degrees of competition (pure competition, monopolistic competition, oligopoly, and monopoly)

  To reduce the current average time the trucks spend

Which alternative would you recommend if you want to reduce the current average time the trucks spend in the system, including service? Show answer.

  Discuss the anticipated impacts upon operating efficiencies

Discuss the anticipated impacts (both positive and negative) upon operating efficiencies, and recommend solutions to minimize the negative impacts.

  Conclude optimal solution to this problem utilizing curves

The Electrotech Corporation manufactures two industrial-sized electrical devices: generators also alternators. Both of these products need wiring also testing during the assembly process. Conclude the optimal solution to this problem utilizing leve..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd