1 A single-phase transformer is wound with 80 turns on the secondary winding and the primary supply voltage is 240 volts, 50 hertz. The minimum core flux is 0.002 Weber. Determine:

(a) the secondary voltage

(b) the primary turns

(c) the secondary load current for a primary load current of 10 amperes. 6

2 A single-phase transformer is used to reduce a 240 volt supply to 12 volts to operate a doorbell. If the primary winding has 480 turns, how many turns must be added to the secondary winding so the transformer can be used for a 30 volt doorbell?

3 A 240/32 volt swimming pool light transformer has a core loss current of 0.5 ampere and a magnetising current of 5 amperes. Use a scale of 20 millimetres per ampere to determine the value and power factor of the transformer's no-load current.

4 A 240/40 volt transformer supplies two different secondary loads. One load (a) draws a current of 12 amperes at a lagging power factor of 0.94. The other load (b) draws a current of 12 amperes at a leading power factor of 0.94. With both loads disconnected, the primary current is found to be 2 amperes at a power factor of 0.173.

Determine the primary current when both the loads are connected.

5 A 10 kVA transformer has an iron loss of 250 watts and a half-load copper loss of 80 watts.

Determine the full-load efficiency at 0.8 power factor.

6 The open circuit voltage of a transformer is 240 volts.

Determine the full-load voltage if the percentage regulation is 8%.

7 An autotransformer has a step-down ratio of 2:1 and the primary is connected to a 415 volt supply. A motor has a normal rated voltage of 415 volts and a starting current of 100 amperes. Determine, with the autotransformer in circuit:

(a) the motor terminal voltage

(b) the starting current drawn from the transformer secondary (assume that the starting current is proportional to voltage)

(c) the current drawn from the 415 volt supply

(d) the current in the common portion of the transformer winding.

8 The design requirements of a 6600 V/400 V 50 Hz single-phase core-type transformer are: Approximate emf/tum: 15 V Maximum flux density: 1.5 T

Find a suitable number of primary and secondary turns, and the nett cross-sectional area of the core.

9 Two single-phase 33 kV/11 kV transformers rated at 400 kVA and 500 kVA are connected in parallel to supply 800 kVA at a pf of 0.85 lagging. The transformers have percent impedances of 5.38% and 6.1% respectively.

Calculate the load on each transformer.

10 The input voltage, current and power to a single-phase load are measured by means of a voltmeter, ammeter and wattmeter respectively, each of these instruments being single-range type. They are connected to the lines by means of a current transformer of ratio 100:5 and a voltage transformer of ratio 50:1.

Draw a circuit diagram to show how the CT, VT and meters are connected into the load circuit. Neglecting instrument and transformer errors, calculate the load kVA and power factor if the voltmeter, ammeter and wattmeter indicate values of 200 V, 2.73 A, and 436 W.

Reference no: EM13862585

Questions Cloud

What are the key parts of a tcp or ip lan plan? : What are the key parts of a TCP/IP LAN plan?
Moving and renaming files and folders are all function of : Copying, moving, and renaming files and folders are all functions of _
Why is marketing research at the core of any marketing plan : Why is marketing research at the core of any Marketing Plan? Assuming you have started to research/think about your team Marketing Plan for the Droneport in Country X; what kind of Marketing research are you planning to use? Have you started g..
Pros and cons of main types of business organizations : Discuss the pros and cons of three main types of business organizations (sole proprietorship, partnerships, and corporations) and determine which would be the best type for the Cardigans.
Calculate the load on each transformer : Two single-phase 33 kV/11 kV transformers rated at 400 kVA and 500 kVA are connected in parallel to supply 800 kVA at a pf of 0.85 lagging. The transformers have percent impedances of 5.38% and 6.1% respectively. Calculate the load on each transfo..
Cracking password management protocols : Identify and describe any obstacles, and explain your solutions for them. Given the access policy, evaluate whether or not Extensible Access Control Markup Language (XACML) could be used to express the contextual attributes.
Compare and contrast frameworks : Compare and contrast the 3 selected frameworks
Calculate the probability of zero patients in the system : Calculate the probability of zero patients in the system (PO), the probability of one patient (P I), and the probability of two or more patients simultaneously arriving during the night shift.
Compare and contrast public and in-house cas : Compare and contrast public and in-house CAs

Reviews

Write a Review

Electrical Engineering Questions & Answers

  Determine the time of operation of 5 amp over current relay

Determine the time of operation of a 5 amp. , 3 sec. over current relay having a current setting of 150 percent and a time setting multiplier of 0.8 connected to supply circuit through a 500 /5 current transformer when the circuit carries a fau..

  Compute power pr absorbed-dissipated in heat

The practical voltage source is formed by combining an ideal voltage source (Vs) and internal resistance (r). 1) Without computing, determine sign of power Ps delivered by voltage source

  Design a voltage divider to provide a voltage

1.5V battery. Design a voltage divider to provide a voltage that is approximately 1/3 of the battery voltage. Use resistances in the kilo ohms range. Redesign your divider so that the resistors are in Mega ohms range.

  What is the range of the sensor voltage outputs

A manufacturer specification sheet lists the transfer function of a pressure sensor as 45±5% mV/kPa with a time constant of 4±10%. A highly accurate test system applies a step change of pressure from 20 kPa to 100 kPa.

  Calculate the total complex power

Calculate the total complex power, total current drawn and the total power factor and Y-connected load with an impedance of (1+ j 6) ohm per phase,

  What distribution on y will max kullback-leibler divergence

Let x and y be Bernoulli randon variables that take on values 1 and 0. X is distrubuted with p = 0.5. What distribution on y will maximize the Kullback-Leibler divergence (D(x||y)

  Calculate the pf at sending end of the transmission line

Three of the above single phase transformers are connected as a 3-phase transformer bank. The high voltage side of the transformer bank is connected in Y and the power is supplied to the transformer bank through a transmission line

  Estimate the mass transfer area

Estimate the mass transfer area per unit volume (a) for this column, estimate the Hoy value for this column and calculate Noy and estimate the height of the column using your answer for Hoy

  Find the attenuation rate after a wave propagates on line

A transmission line is specified by the following, while operated at omega w=6*10^8 rad/s, L'= 0.4*10^-6 H/m, C'=40*10^-12 F/m, G'=80*10^-6 S/m, and R'=20 ohms/m. Find the attenuation rate after a wave propagates 10 meters on this line.

  Determine secondary voltage and the secondary current

An autotransformer with a total of 600 turns has its secondary winding embracing 200 turns. The 600 turns are connectred to a 60Hz, 2400V driving voltage. A load connected to the secondary draws 4.8kVA at 0.6 power factor lagging.

  Suppose you want to move a database from its current

suppose you want to move a database from its current location to a new location and computer that is three hours

  Design an 8085 microprocessor system that has a total

Design an 8085 microprocessor system that has a total of 4Kx8 EPROM space using a single 4Kx8 chip and a total of 4Kx8 RAM using two 2Kx8 chips. The EPROM should be mapped starting at address 0000 hex

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd