problem 1: The ____ trade-off methodology is used to incrementally reduce the project duration with the smallest associated increase in incremental cost.
a. time-quality
b. time-cost
c. schedule-quality
d. cost-production
problem 2: Earliest start time (ES) is the earliest time at which a specific activity can begin
a. calculated on the basis of the project estimated start time and the estimated durations of approaching activities.
b. calculated on the basis of the project estimated start time and the estimated durations of preceding activities.
c. calculated on the basis of the project estimated finish time and the estimated durations of preceding activities.
d. calculated on the basis of the project estimated start time and the estimated durations of succeeding activities.
problem 3: A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities that
a. are near term and those with long durations.
b. are scheduled at the end of the project.
c. are short in duration and can be easily completed.
d. have the lowest cost.
problem 4: Calculate the latest finish for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.
a. Cannot be calculated based upon information given.
b. day 3
c. day 7
d. day 5
problem 5: The estimated types and quantities of resources required for an activity together with the availability of those resources will influence the
a. actual costs of work performed.
b. project scope document description.
c. estimated duration for how long it will take to perform the activity.
d. project's acceptance criteria.