Calculate the irr of the project

Assignment Help Finance Basics
Reference no: EM13692902

The hurdle rate for a possible project being looked at by a firm is 14%. The project is estimated to cost $500,000 now if taken. The estimated net cash inflows for the project for periods 1 through 5 are the following.
period 1 - $0
period 2 - $200,000
period 3 - $225,000
period 4 - $175,000
period 5 - $100,000

(A) Calculate the IRR of the project.
(B) Calculate the NPV of the project.
(C) Should the project be taken? Why or why not?

Reference no: EM13692902

Questions Cloud

Determine the approximate percentage appreciation : Briefly describe and then determine the approximate percentage appreciation or depreciation of the NASDAQ Composite,
Where will be the magnification : An object is placed 40 cm from a convex lens of focal length 20 cm. Where will be the magnification
Find what is the magnification of the system : The image of a tree on a 35 mm color slide is 1.1 mm high. It is to be projected onto a screen 8 m from the slide, and is to appear 643 mm high. What is the magnification of the system
How long should accounts payable : How long should accounts payable be held before payment is made? Explain
Calculate the irr of the project : Calculate the IRR of the project.
Find the density of the hot air in the balloon : A hot-air balloon plus cargo has a mass of 283 kg and a volume of 825 m3. What is the density of the hot air in the balloon
Courtney bennett recently graduated from college : Courtney Bennett recently graduated from college
Calculate the image position : A 1.0-cm-tall object is 60 cm in front of a diverging lens that has a -30 cm focal length. Calculate the image position
Anticipates and addresses possible opposing viewpoints : Anticipates and addresses possible opposing viewpoints

Reviews

Write a Review

Finance Basics Questions & Answers

  Which one of the following is a project cash inflow

Which one of the following is a project cash inflow? Ignore any tax effects.

  The friend corporation issued 100 par value preferred stock

the friend corporation issued 100 par value preferred stock 10 years ago. the stock provided an 8 yield at the time of

  Assessing the appropriate capital structure

Corporations must identify its capital needs prior to assessing appropriate capital structure. The next step is for the firm to undertake all considerations in finishing necessary analysis to ensure its capital structure is suitable.

  Martinez company has decided to introduce a new product the

martinez company has decided to introduce a new product. the new product can be manufactured by either a

  Computation of the npv of the project

Computation of the NPV of the project and What is the NPV for the following project if its cost of capital

  Choose the correct answers and complete the statements

q.1 choose the correct answers and complete the statements.a while evaluating capital investment proposals the time

  Assume emerson electrics managers expect an earnings

you have finally saved 10000 and are ready to make your first investment. you have the three following alternatives for

  Computation of weighted average cost of debt using book

Computation of weighted average cost of debt using book value weights and market value weights.

  Determine the appropriate yellow and all-red interval to use

1. Determine the appropriate yellow and all-red interval to use for each phase. Assume a 10 ft/sec2 deceleration rate, a one second reaction time, and a 20 ft. vehicle length. Round up yellow and all-red times to the nearest ½ second.

  An investor receives a 15 total return by purchasing a

an investor receives a 15 total return by purchasing a stock for 40 and selling it after one year with a 5 capital

  What is the cost of common equity capital for the firm

If the current price of Two-Stage's common stock is $14.20, what is the cost of common equity capital for the firm? (Do not round intermediate calculations. Round answer to 0 decimal places, e.g. 15%.)

  Sensitivity analysis-contingency planning

How does sensitivity analysis relate to contingency planning? What are a couple risk mitigation strategies which you could execute to de-sensitize these variables?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd