Calculate the height of water in the standpipe after 4 hours

Assignment Help Civil Engineering
Reference no: EM13321077

A falling-head permeability test is being conducted on a saturated sample of clayey silt having hydraulic conductivity of 6.5 x 10-9 m/s. The diameter and the length of the sample are 100 mm and 150 mm, respectively. If a 5 mm diameter standpipe is used and the initial height of water in the standpipe (measured from the datum taken at the base of the soil sample) is 1.0 m, calculate the height of water in the standpipe after 4 hours.

Reference no: EM13321077

Questions Cloud

Explain why is acetone added at the end of the reaction : The haloform reaction is executed in this experiment to synthesize benzoic acid from a methyl ketone, acetophenone. Provide an explanation for the following steps in the procedure. a) Why is acetone added at the end of the reaction
What force-acting on the top edge to hold the gate shut : A 6ft wide, 10ft high vertical rectangular gate has its top edge 6ft below the water level. it is hinged along its lower edge. what force, acting on the top edge, is necessary to hold the gate shut
Construct a sustained argument in response to the question. : Construct a sustained argument in response to the question.
Net domestic product and gross national product : Distinguish between Intermediate goods and final goods
Calculate the height of water in the standpipe after 4 hours : A falling-head permeability test is being conducted on a saturated sample of clayey silt having hydraulic conductivity of 6.5 x 10-9 m/s. The diameter and the length of the sample are 100 mm and 150 mm.
Calculate the buoyant force acting on the balloon : A large balloon of mass 233 kg is filled with helium gas until its volume is 327 m3. Assume the density of air is 1.29 kg/m3, Calculate the buoyant force acting on the balloon
Explain which a mixed solvent recrystallization method : Briefly explain the circumstances under which a mixed solvent recrystallization method would be used to recrystallize a given compound.
Find the pressure head at the lower end of the pipe : A vertical pipe of 4ft diameter and 60 ft long has a pressure head of 22.7 ft of water at its upper end. when the flow of water through it is such that the mean velocity is 16 fps, the pipe friction head loss is hf = 2.8 ft.
Distinguish between current account and capital account of : Distinguish between current account and capital account of balance of payment account. Mention any two transactions of capital account.

Reviews

Write a Review

Civil Engineering Questions & Answers

  Determine the effective size as well as the uniformity

Determine the effective size as well as the uniformity coefficient and coefficient of curvature for each soil. Determine also the percentages of gravel, sand, silt, and clay according to (a) ASTM, (b) AASHTO, (c)USCS, and (d) the British Standard.

  What will be the mass of the rod at the end of 20 mins

A common commercial process for the production of so-called "Electronic Grade Silicon" (EGS) is the Siemens process (see figure below). EGS is of ultra-high purity, enough to be used for fabrication of microchips.

  Determine what is the hydraulic conductivity of the sand

it was observed that the quantity of the water flowing through the sand layer into the collection ditch is 250 m^3/day. What is the hydraulic conductivity of the sand (k)

  Average waiting time in the queue

What is the average length of queue, the average time spent in the system, and the average waiting time in the queue?

  Determine the required pumping rate of the construction

It is required to dewater a construction site 80 m by 80 m. The bottom of the construction will be 1.5 m below the initial water surface elevation of 90 m. Four pumps are to be used in 0.5-m diameter wells at the four corners of the site.

  Determine the tensions in the cables and the reactions

The suspended load exerts a force F = 600 lb at A and bar OA weighs 200 lb. Assume that the bar's weight acts at its midpoint. Determine the tensions in the cables and the reactions at the ball and socket support O.

  What is the estimated uncertainty in the length of vector

The base line vector between the base and roving reciever is 8340m and has an accuracy of +/-(1to 2 cm +/-2ppm). What is the estimated uncertainty in the length of this vector

  What is the annualized cost of system in dollars per year

An emission control system for a new car costs $750 and reduces NOx emissions from 0.4 g/mile to 0.18 g/mile. Assume the car is driven 10000 miles per year, and the life of the emissions control system is 11 years

  Strength of a semicrystalline polymer

Briefly explain how each of the following influences the tensile or yield strength of a semicrystalline polymer and why: (a) Molecular weight (b) Degree of crystallinity (c) Deformation by drawing (d) Annealing of an undeformed material

  Determine what will be the hydraulic conductivity of the gcl

If this GCL is used as a liner beneath a 55-ft high landfill with a waste unit weight of 45 lb/ft3, what will be the hydraulic conductivity of the GCL at the bottom of the landfill

  Determine what is the rate of water to be added to the tank

A hole at the bottom of a fish tank releases water at a rate given by the free jet equation. The hole at the bottom has a .5" diameter. If the water level is desired to be at 2' high and be at steady state,

  How many moisture of aggregate will be needed

Base course aggregate has a target dry density 119.7 lb/cu ft in place. it will be laid down and compacted in a rectangular street repair area of 2000 ft x 48 ft x 6 in the aggregate in the stockpile contains 3.1% moisture.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd