Project Status Report (time based)

Project reporting is the act of collecting and distributing project information. Project information is distributed to many groups of stakeholders and should be adapted to provide information at an appropriate level, format, and detail for each type of stakeholder

2 GANTT CHART WITH BUDGETED COST
This chart represents the original baseline plan for the project.

3 ACTUAL PERFORMANCE
This chart represents the work performed with the actual cost incurred. The data date is the end of week 8.
4 VARIANCE ANALYSIS
Complete the table below. Calculate the values at the data date and show the formula used.
Describe the current status of the project in terms of time and cost performance.

5 FORECASTS- VALUES AT COMPLETION
Calculate the following forecast values and motivate your choice of the EAC formula used
6 FORECAST COMPLETION DATE
Even though a more accurate forecast completion date is derived from the updated schedule, the forecast duration could also be derived from the Schedule Performance Index (SPI) and can help forecasts the end date of the project (see AS 4817-2006 pp.13-15 Section 2.3.2).

Calculate the forecast project duration using the SPI of the project at the data date.

7 MILESTONE REPORT
8 ISSUES, RISKS AND OTHER MATTERS
Include any other matters for reporting such as issues, risks and any other relevant matters and their potential impact on the project in the future, that need to be brought to the attention of the stakeholders.

9 LEARNING FROM THIS EXERCISE
Describe in your own words what you have learned from this exercise. E.g. would comparing the budget with actual cost alone have given an accurate picture of the project?

Assessment 1 Part B
Exception Report (event based)

1. PROJECT INFORMATION
2. ESTABLISH THE NEED FOR AN EXCEPTION REPORT
3. EXCEPTION REPORT
4 LEARNING FROM THIS EXERCISE

Question 1 What are the differences between a time-based report and an events-based report?
Question 2 What are the advantages and disadvantages of an events-based report for the project?
Question 3 What are the advantages and disadvantages of an events-based report for the project manager and the project management team?

Attachment:- Assessment - Project Status and Exception Report exercise and template.rar

Reference no: EM132494857

Questions Cloud

Novel value proposition within an existing business : Report for a novel value proposition within an existing business or organisation. You must use appropriate headings to structure the body of the report
Prepare all necessary journal entries in for both situation : Prepare all necessary journal entries in 2019 for both situations. Hatcher Cosmetics acquired 10% of the 200,000 ordinary shares
What is the net cost of the goods if sultan crop pays : What is the net cost of the goods if sultan crop pays within the discount period? Sultan Corp. Purchased merchandise inventory
What will be the required balance of the dtl at the end : With relation to the accounts receivable, What will be the required balance of the DTL at the end of the year? The final balance of the allowance for doubtful
Calculate the forecast project duration using the spi : What are the differences between a time-based report and an events-based report and What are the advantages and disadvantages of an events-based report
Make schedule to estimate amount of uncollectible accounts : It is rumored that the customer will be filing for bankruptcy in the near future. As controller for Rough Stuff, how would you handle this situation?
How important has the federal government involvement : How important has the Federal Government's involvement beenin the proliferation of home loans in the United States?
What are the steps in the underwriting process : What are the steps in the Underwriting Process? Describe the steps.
What is the purpose of the hud-fha 203 : What is the purpose of the HUD/FHA 203(k) Rehabilitation Home Mortgage Insurance program?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd