Calculate the expected time and variance for each activity

Assignment Help Operation Management
Reference no: EM131357137

The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent.

Activity

Immediate Predecessors

Time (Weeks)

a

m

b

A

-

9

10

11

B

-

4

10

16

C

A

9

10

11

D

B

5

8

11

a) Calculate the expected time and variance for each activity.

b) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network?

c) What is the variance of the critical path? What is the variance of the other path in the network?

d) If the time to complete path A-C is normally distributed, what is the probability that this path will be finished in 22 weeks or less?

e) If the time to complete path B-D is normally distributed, what is the probability that this path will be finished in 22 weeks or less?

f ) Explain why the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less?

Reference no: EM131357137

Questions Cloud

Write a paper wrote on the judge samson from the bible : Write a paper wrote on the Judge Samson from the Bible.- While most anything we talk about in the semester, or readings in the text is a possible paper topic, it cannot be something too general.
Why do we develop alternative physical designs : Describe two situations in which you would use each of the following techniques: internal literature review, interview, internal presentation, observation, walkthrough, database and files review, and questionnaire.
Write a response about the given post : Global crimes transcend national borders and threaten American citizens and communities, businesses, and institutions, as well as global security and stability. The classification of global crimes can be categorized according to if the behavior is..
Compare and contrast those two triggers : The chapter differentiates two different "triggers" for the systems development process: a planned, periodic review and a user-requested systems development. Compare and contrast those two triggers.
Calculate the expected time and variance for each activity : Calculate the expected time and variance for each activity. What is the expected completion time of the critical path? What is the expected completion time of the other path in the network
Discuss the most important risk for juvenile delinquency : Discuss the most important risk and protective factor for juvenile delinquency. Support your answer. What intervention or prevention can we use to reduce the effects of your chosen risk factor?
Summarize the youth victimization : Summarize the "Youth Victimization: Prevalence and Implications" report. In your assignment, discuss the strengths and weaknesses of this study. Do you agree with the findings of this report? Why or why not?
Define the new customer-purchasing journey : Define the new customer-purchasing journey - Define strategies to identify and influence the new consumer and strategies to engage, nurture, and utilize brand advocates to spread your message
Identify the four steps of integrative negotiation process : In 2010, New York State passed a law that required its school districts to develop more stringent teacher-evaluation systems. Local school districts and their unions were assigned a task for specifying certain criteria of their new systems by Janu..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd