Kristen and Marlon own K&M, a company that produces cable assemblies. Business has been good so Kristen and Marlon have decided to expand their product line to include a new cable product, which will be manufactured in the current facility. They have decided to use a project management approach to bring the new product on line, and have identified 11 activities and their precedence relationships:

Activity description Predecessor A M B Crash time Normal cost Crash Cost
A Develop product specs None 2 4 6 3 8000 11000
B Design manufacturing process A 3 6 9 5 30000 35000
C source/purchase materials A 2 3 4 2 6000 6000
D Source and purchase equipment B 4 6 8 4 24000 28000
E Receive equipment D 8 15 16 12 60000 72000
F Receive materials C 2 5 8 4 5000 6500
G Pilot production run E, F 2 2 2 2 6000 6000
H Evaluate product design G 1 2 3 2 4000 4000
I Evaluate process performance G 2 3 4 2 4000 5000
J Write documentation report H, I 2 4 6 2 4000 6400
K Transition to manufacturing J 2 2 2 2 5000 5000

1. Construct a network diagram
2. Calculate the expected time and variance for each of the project activities?
3. Calculate the ES, EF, LS and LF times?
4. Find the critical path for this project?
5. Determine which activities have slack time and how much it is for each one?
6. Determine the expected completion time for the project?
7. If Kristen and Marlon want to finish their project in 36 weeks, how should they proceed?

Reference no: EM13234592

Questions Cloud

What is the flow speed of the medicine through the needle : A 2.50mL syringe has an inner diameter of 6.00mm , a needle inner diameter of 0.290mm , and a plunger pad diameter of 1.2 cm, What is the minimum force the nurse needs to apply to the syringe
What are zoning laws : What are zoning laws? How do they affect the location decision and why may a cheap location not be the best location?
Explain the ammonium nitrate has completely decomposed : Suppose we have a flask with a movable piston in which pressure is kept constant at 1.00atm. If an 8.00gram sample of solid ammonium nitrate is introduced into the flask what is the volume of the flask in liters at 298K when the ammonium nitrate h..
What happens to the equilibrium level of income or output : Suppose that households are concerned about the future and cut back on their marginal propensity to consume from 0.80 to 0.667. Try this experiment for the Money Supply Target case and the Interest Target Case.
Calculate the expected time and variance : Kristen and Marlon own K&M, a company that produces cable assemblies. Business has been good so Kristen and Marlon have decided to expand their product line to include a new cable product, which will be manufactured in the current facility.
The naoh are required to completely neutralize the solution : required to reach the first equivalence point of a solution of citric acid (H3C6 H5O7), how many ml of NaOH are required to completely neutralize this solution
Write an isr in c to add the signed value on port t (ptt) : Write an ISR, in C, to add the signed value on PORT T (PTT) to the byte value stored in location data1.
What is the block''s mass density : A 2.0cm×2.0cm×6.0cm block floats in water with its long axis vertical. The length of the block above water is 1.0cm
Explain what is the mass flow rate of the stream : Liquid Chlorobenzene flows through a pipe at a rate of 3M^3/min. What is the mass flow rate of the stream in kg/h. What is the molar flow rate in mol/s

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd