Calculate the expected completion time

Assignment Help Marketing Management
Reference no: EM13737096

Objectives:

Determine the critical path identified by a given PERT/CPM analysis.
Utilize PERT analysis to determine the probability that a given project will meet a specified deadline for completion.
Determine slack time for a given project activity.
Determine scheduled start time for a given project activity.
Determine scheduled completion time for a given project activity.
Use time-cost trade-offs to appropriately crash a project network.

Given: Company A is installing a Web-based customer-feedback system to meet customer needs for quick response when rolling out new products. A new product line is rolling out in 34 weeks and the customer-feedback system must be installed and running in time for the new product launch.

Table shows three estimates of the time it will take Company A to complete each of the activities and project tasks in the customer feedback system project (optimistic, probable, pessimistic). Company B is installing a similar feedback system to accompany a new product line and originally had the same time line as Company A. Company B just announced that its new product line is ahead of schedule and will be launched in 30 weeks instead of the initially projected 34 weeks. Because the Web-based customer feedback system must be installed and running in time for the revised date of the product launch, something must be done to shorten implementation time required for the customer-feedback system project. Refer to Table 1.2 in the attached worksheet "PERT/CPM Tables" that lists the expected time it will take to complete the activities if shortened as much as possible (crash time), the cost to
complete the activity using normal resources (normal cost), and the cost of completing the activity on an accelerated basis (crash cost).

Task:

A. Use the estimates for Company A in Table 1.1 to do each of the following:

1. Determine the expected completion time for each of the ten project activities, entering all your answers in Table 1.1 and showing all your work.

a. Determine the variance for each project activity to two decimal places, entering all your answers in Table 1.1 and showing all of your work.

2. Prepare a PERT chart (network diagram) and identify the critical path for project completion, using your calculated values from part A.

3. Determine each of the following, showing all of your work or reasoning:

a. Expected duration of the entire project
b. Slack for project task A
c. Slack for project task H
d. The week project task F is scheduled to start
e. The week project task I is scheduled to finish

4. Determine the probability of completing this project in time for the product launch in 34 weeks, showing all your work.

B. Assume that Company B has the same expected completion times for project activities as Company A. Use your results from part A1 to calculate the following information, entering all answers in Table 1.2 and showing all of your work:

1. Maximum reduction in time
2. Crash cost per week

C. Identify the following by using your results from part B:

1. Activities to be crashed in order to complete the project within 30 weeks.
2. Number of weeks each of these activities should be crashed to meet the deadline with the lowest possible increase in cost.
3. Additional crashing cost of the activities identified in part C1.

Reference no: EM13737096

Questions Cloud

How has the composition of government spending changed : How has the composition of government spending changed since the 1960's? Support your answer with examples from the article.
Compensation plan outline : Evaluate the existing compensation plan to determine if it is the most appropriate for your company. Explain your rationale.
How your topic relate to what we have discussed in class : How does it relate to what we've discussed in class? Why is it important? What can we learn from it today? Why did you choose this document or artifact? What is it?
Analyze master improvement plans and review plans : Analyze master improvement plans and review plans used to achieve long-term improvement efforts.
Calculate the expected completion time : Determine the critical path identified by a given PERT/CPM analysis. Determine the expected completion time for each of the ten project activities, entering all your answers in Table 1.1 and showing all your work
Calculate the expected completion time : Determine the critical path identified by a given PERT/CPM analysis. Determine the expected completion time for each of the ten project activities, entering all your answers in Table 1.1 and showing all your work
What will be your financial break-even point : What will be your financial break-even point. If you require investment capital, identify possible sources (friends, family, banks, USSBA, etc.).
Human resources planning and employee relations : Building on the work that you completed in Assignment continue evaluating the role of functions HR in creating a set of Human Resources' policies and procedures for the acute care hospital.
What is the budgeted accounts receivable balance : What is the budgeted accounts receivable balance from July sales on July 31?

Reviews

Write a Review

Marketing Management Questions & Answers

  Integrated marketing communication

Developing an IMC plan of Amazon that aims to create awareness and knowledge amongst Singaporean  consumers of the ethics involved in buying clothing made from Bangladeshi factories  .

  Multiple choice questions on e-commerce

The assignment in Computer Science or Information Technology is about multiple choice questions, particularly in e-commerce. Questions such as types of e-commerce websites, commercial websites, disintermediation, Platform for Piracy, the data that ca..

  Balanced scorecard for red lobster

The assignment in marketing is about Red Lobster, which is one US and Canada's most loved seafood restaurant. It has hundreds of outlets in US and Canada and it now wants to expand further. The approach adopted by Red Lobster has been discussed in fu..

  Marketing plan - marketing audit, swot and smart report

The assignment in marketing is about preparing a marketing plan. As part of marketing plan, the SWOT analysis, assessing the competitive position, identifying critical competitive issues, marketing objectives, strategy and actions have been suggested..

  Marketing plan

Marketing deals with preparing a marketing plan for either an existing product or a new product. Various aspects about launching a new product into the market are discussed ranging from the industry the product belongs to, goals and vision of the com..

  Yamato corporation analysis - harvard case study

Please refer to the PDF for the Case Study and questions.The case study from Harvard Business School is about Yamato Corporation, a parcel delivery company which provides door to door delivery in Japan.

  Marketing plan - create a new product

The assignment in marketing is about competitive analysis for a new product namely "heated insoles". These heated insoles can be put in shoes and they can protect the wearer's feet by keeping them warm during cold winters.

  Report on digital marketing strategy for a website

Promotion strategies of  the one's own developed website

  Integrated marketing campaign of mccafe

Integrated marketing campaign for McDonald's McCafe. McCafe has been launched in Canada. This is a case study which involves the use of digital marketing and social media marketing apart from regular marketing such as TV and radio. All these more are..

  New product development at adidas

In this paper, the researcher also determines the different kind of practices used by Adidas to manufacture shoes for its customers.

  Managing services in competitive environment

Services can be defined as separately identifiable, intangible activities which provide want-satisfaction when marketed to household consumers and/or industrial users.

  Prepare a marketing plan

A marketing plan is an essential tool for any marketer, providing direction for a brand, product or organization. A marketing plan describes the marketing environment, marketing objectives and marketing strategies.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd