A 2000 ft vertical curve connects to a +3% grade to a -5% grade. If the vertical tangents intersect at station 52+60.55 and elevation 877.62 ft, calculate the elavations at the VPC, VPT, high point and station 54+00.
The force is applied at the two pins. The pins allow rotation around the z-axis and do not allow rotation around the y-axis. The length of the beam between the pins is 8m. Determine the maximum allowable compressive force that can be applied.
What return period must an engineer use in the design of a bridge opening for 50% risk that flooding will occur at least once in two successive years
Design a simply supported one-way reinforced concrete floor slab to span 10 ft and carry a service live load of 175 psf and a service dead load of 25 psf. Use fc' = 3000 psi and fy = 60,000 psi. Make the slab thickness to ½-in. increments.
A 4.00-cm-diameter, 0.80-m long rod of aluminum 7075-T6 is subjected to an axial tensile force with a factor of safety of 1.75. The yield stress and modulus of elasticity of aluminum 7075-T6 are 500. MPa and 210. GPa, respectively.
What is the maximum column load in kips that could be placed on a 4-ft square temporary footing on a sand for which the standard resistance is about N=15 and the water table is at the surface
The pipe contains two 6 in steel elbows, two fully open gate valves, a fully open 90o angle valve, and a swing check valve. If the discharge end of the pipe is located 20 ft higher than the entrance, what is the pressure difference between the two..
design a rectangular reinforced concrete beam (tension steel only) for the span and superimposed service loads shown. use f'c=5000psi and A615 grade 60 steel. LL=3.5 k/ft over the first 12 feet of the beam
Find the swell for a soil which weighs 1600kg/m in bank and 1300kg/m3 in bank and 1300kg/m3 Loose and what is the shrinkage factor for a mass of soil that takes up 1.5m3 in bank and reduces down to 1.2m3 after compaction
If the pressure in pipe B is decreased 10 kPa and the pressure in pipe A remains unchanged, determine the new reading along the inclined leg of the mercury manometer.
On a very hot day, I saw a 1.6 meter long steel bar held between two rigid supports that had buckled due to the heat. The bar had a cross section of 10 mm by 40 mm, and I assume was A36 steel.
Design the ramp for the highest design speed (to the nearest 5 mph) without exceeding a minimum D of 8.0. (Assume the PC of the horizontal curve is at station 15+00, and the vertical curve PVIs are at the PC and PT of the horizontal curve). Maximu..
Water at 20ºC flows at a velocity of 2 m/s in a 200-mm diameter horizontal ductile-iron pipe. a) Estimate the friction factor in the pipe, and state whether the pipe is hydraulically smooth or rough
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd