Calculate the earliest start and finish times

Assignment Help Project Management
Reference no: EM13211070

1. Based on the data below:

(a) Draw a network diagram for the project, highlight the  "normal" critical path

(b) Calculate the earliest start and finish times, the latest start and finish times and the slack days for each activity based on normal durations

(c)  If indirect costs of £375 per day could be saved by reducing the overall duration of the project,  what is the minimum cost for the project?

(d) What practical factors should be considered before an activity is crashed?

(e) Describe a practical approach to monitoring the progress of a project like this one.

Activity

Preceded by

Normal days

Crash days

Normal cost (£)

Crash Cost (£)

A

-

4

3

800

900

B

-

6

3

1000

1600

C

-

4

3

900

1200

D

A

5

3

700

1200

E

B,C

4

3

600

750

F

D,E

3

3

400

400

G

F

4

3

800

850

H

F

8

3

1200

3200

I

G,H

9

3

1200

3300

J

H

3

3

600

600

K

J

5

3

2000

2800

L

I,K

7

3

6500

5000

2. Based on the data below calculate the probability that the project will be completed in 20 days or less and discuss the practical considerations that would be relevant if a company doing this project faced a penalty for completion in more than 20 days. What action could be taken to improve the chances of completion within a  20 day period?

Activity

Preceded by

Optimistic days

Most likely days

Pessimistic days

A

-

2

3

4

B

-

4

6

8

C

A,B

6

9

12

D

A,B

4

5

12

E

C,D

3

5

7

Reference no: EM13211070

Questions Cloud

Explain vessel of fixed volume and at a temperature : The two phases are allowed to come to equilibrium with their product ammonia in a vessel of fixed volume and at a temperature
State the equivalence volume ve of the titration in ml : consider the titration of 25.00ml of 0.650 M propanoic acid, HC3H5O2 ( Ka = 1.3 X 10^-5), with 0.750 M sodium hydroxide, NaOH, and answer the following questions?
Find out the minimum concentration of koh required : Potassium hydroxide is used to precipitate each of the cations from their respective solution. Determine the minimum concentration of KOH required for precipitation to begin in each case.
Explain herbigon is dissolved in 1 m acetic acid : As a chemist for an agricultural products company, you have just developed a new herbicide,"Herbigon," that you think has the potential to kill weeds effectively
Calculate the earliest start and finish times : Calculate the earliest start and finish times, the latest start and finish times and the slack days for each activity based on normal durations and draw a network diagram for the project
Explain the ph change of solution of citric acid : What is the pH change of a 0.200M solution of citric acid (pKa=4.77) if citrate is added to a concentration of 0.175M with no change in volume?
What is the effect of temperature on compressive strength : what is the effect of temperature on compressive strength of concrete?
Build a balanced scorecard for the unit of the organization : Build a Balanced Scorecard for the unit of the organization for which you work, or have worked. Unless you are in senior management, focus on the unit with which you are most familiar rather than the organization as a whole
Explain alcohols generally require acid catalyst : Alcohols generally require acid catalyst in order to undergo substitution by nucleophiles. The acid catalyst enhances the reaction by

Reviews

Write a Review

Project Management Questions & Answers

  Musical event project management

Woods Ltd have employed you as a consultant to manage this one off special project

  Duration estimation techniques in project management

In a short response, describe the advantages and disadvantages for each of the five techniques. Include an example of when it is appropriate to use each technique.

  Why the family is in need of the project

Briefly explain why the family is in need of the project and show the expected benefits that are motivating the family to commission this project.

  Techniques estimating time and cost in projects

Discuss the techniques that companies are using today for estimating time and cost in their projects.

  Risk management is important factor in technology

Risk management is an important factor in SaveWithUs' effective use of technology.

  Find the resources necessary to complete the project

Benefits from completing the project and how much will it cost, hours material, methods, ect. How long will the project take

  Computing number of units to purchase

Projected sales for August, September, and October are 25,000 units, 20,000 units, and 30,000 units, respectively. How many units must be purchased in September?

  Show the project scope statement

Explain how do you see the Project Charter content feeding into the Project Scope Statement?

  Macrs calculations

MACRS calculations - what is the after-tax cash flow from the sale of machinery

  Materials requirements planning systems

Materials requirements planning systems are advantageous in that they

  Points of the project scope checklist

Briefly explain the first five points of the Project Scope Checklist in relation to your project and What are the project objectives?

  Emotional intelligence - importance for project managers

Self-awareness refers to a person's capacity for being aware of how they are feeling and managing emotions refers to a person's capacities to ensure that feelings do not interfere with getting things accomplished.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd