Calculate the direct materials price and quantity variances

Assignment Help Managerial Accounting
Reference no: EM133132095

Question - Luckett Company's standards call for two feet of direct materials for each unit. The standard price of one foot is $2. Actual production was 50,000 units requiring 105,000 feet of direct materials. Luckett purchased 107,000 feet at a unit price of $2.1 per foot.

Calculate the direct materials price and quantity variances and indicate whether the variances are favorable or unfavorable.

Reference no: EM133132095

Questions Cloud

What is actual cost of the Direct Materials Used per pound : Direct materials standard (2 pounds per unit @ $0.53/lb.) $1.06 per finished good. What is actual cost of the Direct Materials Used per pound
Calculate diluted earnings per share for the year ended : The average market price of the company's shares during 2020 was $25. Calculate diluted earnings per share for the year ended December 31, 2020
Journalize and post the adjusting entries : Supplies were purchased on January 1, 20X1, inventory of supplies on January 31, 20X1, is $850. Journalize and post the adjusting entries
Dimensions of information systems strategic planning : Summarise your findings, consolidating and drawing attention to the main points of the report - State an introduction of the case
Calculate the direct materials price and quantity variances : Calculate the direct materials price and quantity variances and indicate whether the variances are favorable or unfavorable
What is the ending raw materials inventory : Assume the following Information from a schedule of cost of goods manufactured: Purchases of raw materials $60,000. What is the ending raw materials inventory
What amount would not be covered by his insurance : Three others were awarded damages of $154,000, $65,000, and $81,000. What amount, if any would not be covered by his Insurance
Why will land almost always increase in value : He would develop the land around it, and then sell that for a big profit 2 decades later. Why will land almost always increase in value
Calculate the amount of interest earned from the investment : Evan invested $1,700 at the beginning of every 6 months in an RRSP for 11 years. Calculate the amount of interest earned from the investment

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd