Reference no: EM13860252
Examine the following EVM data for the Acme project, a hypothetical construction project, to view information on the past and future performance:
*Cumulative planned value (PV) = 550
*Cumulative earned value (EV) = 475
*Cumulative actual cost (AC) = 525
*Budget at completion (BAC) = 1000
After evaluating the Acme project, do the following:
1. Calculate the cost variance (CV), schedule variance (SV), cost performance index (CPI), and schedule performance index (SPI). Using these four metrics, briefly explain whether the project is ahead or behind for cost and schedule performance.
2. Using the results from the first question, calculate the Estimate at Completion (EAC) and Variance at Completion (VAC). Analyze the results and explain whether the project is likely to overrun or under run the baseline plan and by how much.
*Make sure that you include formulas in the spreadsheet so that calculations can be checked!
Write a method called drawspokes to draw the spokes
: Write a method drawForest that draws the trees using the method drawTree from Part B. The method takes as a parameter the number of trees to draw
|
Change in the total quantity produced
: The change in the total quantity produced which results when one more worker is added to the production process is called
|
Does the government and big business control
: To what extent in life can people make choices to suit us and our own good? Or does the government and big business control us, de facto, or not, (and to what extent)?
|
Composite index for housing construction costs
: Prepare a composite (weighted) index for housing construction costs in 2008 with the following data:
|
Calculate the cost variance-schedule variance
: Examine the following EVM data for the Acme project, a hypothetical construction project, to view information on the past and future performance: Calculate the cost variance (CV), schedule variance (SV), cost performance index (CPI), and schedule per..
|
What challenges do owners of biotechnology companies face?
: What challenges do owners of biotechnology companies face?
|
How designers influence your emotions about those concepts
: What are the ways that designers force us to focus on necessary concepts of a play, or how designers force your focus to necessary concepts of the play? and How designers influence your emotions about those concepts?
|
How organizations line of business affect decision of ais
: How does the organization's line of business affect the decision of its AIS? Give several examples of how difference among organizations are reflected in theirs AIS.
|
Optimal consumption of coffee and milk
: Boris budgets $9 weekly for his morning coffee with milk. He likes it if it is prepared with 4 parts coffee, 1 part milk. (Milk and coffee are perfect complements here). Coffee costs $1/oz, and milk $0.5/oz. Draw his budget constraint and indifferenc..
|