Reference no: EM13973150
Earned Value Exercise
Complete the following problems:
1. The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.
Task
|
Predecessors
|
Duration in days
|
Planned Value ($)
|
Actual Cost ($)
|
Percent Complete
|
A
|
None
|
2
|
550
|
700
|
100
|
B
|
None
|
3
|
950
|
1450
|
100
|
C
|
A
|
2
|
300
|
350
|
50
|
D
|
A
|
5
|
700
|
650
|
20
|
E
|
B ,C
|
6
|
1000
|
350
|
10
|
To do this exercise, it is best to start with a Gantt chart depicting the task relationships.
CV ______________________
CPI ________________
SV ______________________
SPI ________________
EAC _____________________
2. Using the following information below, calculate the cost performance index and the schedule performance index. Then calculate the estimate at completion
Planned value: 7700
Earned value: 7100
Actual costs: 7900
Budget at completion: 39900
CPI _______________________
SPI _____________________________
EAC ______________________
3. The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.
Task
|
Predecessors
|
Duration in days
|
Planned Value ($)
|
Actual Cost ($)
|
Percent Complete
|
A
|
None
|
3
|
700
|
750
|
100
|
B
|
A
|
5
|
1100
|
1400
|
100
|
C
|
A
|
2
|
250
|
300
|
100
|
D
|
A
|
5
|
900
|
600
|
100
|
E
|
B ,C
|
6
|
1300
|
1200
|
100
|
F
|
C
|
10
|
11000
|
12500
|
75
|
G
|
F
|
7
|
900
|
0
|
0
|
H
|
G
|
8
|
1500
|
0
|
0
|
To do this exercise, it is best to start with a Gantt chart depicting the task relationships.
CV ______________________
CPI ________________
SV ______________________
SPI ________________
EAC _____________________
4. Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary's team has completed five tasks which had a combined planned value of $8800. However, the team spent $9200 to complete those tasks. She has five additional tasks to complete the project. What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary's project?
5. Consider the following information:
PV=6700
EV=5200
AC=7400
BAC=32000
Expected Duration=12 weeks
Calculate the following:
CV __________________
SV __________________
CPI __________________
SPI __________________
EAC __________________
Duration at Completion _______________
Description of each organized crime group
: A description of each organized crime group. The theory, or theories, of organized crime behavior that you think best explains the criminal behavior of members of the two groups
|
Determine the location of the image seen by that observer
: A small ball is placed in front of a plane mirror, as shown in the top view diagram. Which observer(s), if any, can see an image of the ball in the mirror? Sketch a ray diagram that supports your answer.
|
Overseas customer and the special discounted price
: Suppose there is ample idle capacity to produce the units required by the overseas customer and the special discounted price on the special order is $81.90 per unit. By how much would this special order increase (decrease) the company's net operat..
|
Create a network diagram and explain in detail
: Each switch connects to a centralized router on a different interface, giving one subnetwork for each floor of the network, plus one for the server farm, one for the DMZ, and one for the Internet. Determine how many ports the router needs.
|
Calculate the cost performance index
: Using the following information below, calculate the cost performance index and the schedule performance index. Then calculate the estimate at completion
|
How many nm did it travel
: Your true heading is 100 and your magnetic variation is 4W , What is your magnetic heading ? true airspeed is 105 KTAS you have a 15 knot tail wind how far would you travel in SM in 35 min?
|
Determine the net income of a company
: Determine the net income of a company for which of the following information is available for the month of July. Employee salaries expense $197,000 Interest expense 27,000 Rent expense 37,000 Consulting revenue 468,000
|
Which path requires more work
: A ball of mass 0.18 kg moving with speed 11.3 m/s collides head-on with an identical stationary ball. (Notice that we do not know the type of collision.) Which of the following quantities can be calculated from this information alone?
|
Was the decision to offshore successful
: How well did GlobShop manage the change process after making the decision to offshore? Was the decision to offshore successful? Defend your answers.
|