Earned Value Exercise

Complete the following problems:

1. The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

2

500

650

100

B

None

3

1000

1500

100

C

A

2

200

300

50

D

A

5

600

600

20

E

B ,C

6

1200

550

10

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________     CPI ________________

SV ______________________      SPI ________________

EAC _____________________

2. Using the following information, calculate the cost performance index and the schedule performance index. Then calculate the estimate at c

Planned value: 6700

Earned value: 6100

Actual costs: 7300

Budget at completion: 38900

CPI _______________________                    SPI  _____________________________

EAC ______________________

3. The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

3

600

650

100

B

A

5

1000

1500

100

C

A

2

200

300

100

D

A

5

1000

600

100

E

B ,C

6

1200

1200

100

F

C

10

10000

12000

75

G

F

7

700

0

0

H

G

8

1600

0

0

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________     CPI ________________

SV ______________________      SPI ________________

EAC _____________________

4. Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary's team has completed five tasks which had a combined planned value of $7800. However, the team spent $8200 to complete those tasks. She has five additional tasks to complete the project.  What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary's project?

5.  Consider the following information:

PV=6500

EV=5000

AC=7200

BAC=32000

Expected Duration=12 weeks

Calculate the following:

CV __________________

SV __________________

CPI __________________

SPI __________________

EAC __________________

Duration at Completion _______________

Reference no: EM131487829

Questions Cloud

Is the p-b ratio justified by the forecasted roce : Valuing Dividends or Return on Equity: General Motors Corp (Easy) In April 2005, General Motors traded at $28 per share on book value of $49 per share.
Benefits and limitations of approach for us labor movement : In a 2-3 page essay, discuss the benefits and limitations of this approach for the U.S. labor movement today.
What does your analysis tell you about long-run growth rate : Converting Analysts; Forecasts to a Valuation: Nike, Inc. (Medium) Nike reported book value per share of $15.93 at the end of its 2008 fiscal year.
Health care delivery system in the united states : Managed Health Care has significantly affected the Health Care Delivery system in the United States. In your own words, describe Managed Health Care.
Calculate the cost performance index : Using the following information, calculate the cost performance index and the schedule performance index.
Good leadership and effective leadership : What do you think is the difference between "good" leadership and "effective" leadership? Provide examples.
What is the revised forecast of return on common equity : Residual Earnings Valuation and Accounting Methods (Hard) Refer back to the valuation. In that proforma, an analyst forecast $388 million of earnings for 2013.
Calculate her debt safety ratio : Alyssa Clark is evaluating her debt safety ratio. Calculate her debt safety ratio.
Comprehensive needs assessment handled : How is a comprehensive needs assessment handled in event management and planning?

Reviews

Write a Review

Management Information Sys Questions & Answers

  Information technology and the changing fabric

Illustrations of concepts from organizational structure, organizational power and politics and organizational culture.

  Case study: software-as-a-service goes mainstream

Explain the questions based on case study. case study - salesforce.com: software-as-a-service goes mainstream

  Research proposal on cloud computing

The usage and influence of outsourcing and cloud computing on Management Information Systems is the proposed topic of the research project.

  Host an e-commerce site for a small start-up company

This paper will help develop internet skills in commercial services for hosting an e-commerce site for a small start-up company.

  How are internet technologies affecting the structure

How are Internet technologies affecting the structure and work roles of modern organizations?

  Segregation of duties in the personal computing environment

Why is inadequate segregation of duties a problem in the personal computing environment?

  Social media strategy implementation and evaluation

Social media strategy implementation and evaluation

  Problems in the personal computing environment

What is the basic purpose behind segregation of duties a problem in the personal computing environment?

  Role of it/is in an organisation

Prepare a presentation on Information Systems and Organizational changes

  Perky pies

Information systems to adequately manage supply both up and down stream.

  Mark the equilibrium price and quantity

The demand schedule for computer chips.

  Visit and analyze the company-specific web-site

Visit and analyze the Company-specific web-site with respect to E-Commerce issues

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd