Calculate the cost and the quoted price of a gc

Assignment Help Managerial Accounting
Reference no: EM132960270

Builders Limited is a building business that provides a range of building services to the public. Recently they have been asked to quote for garage conversions (GC) and extensions to properties (EX) and have found that they are winning fewer GC contracts than expected. Builders Limited has a policy to price all jobs at budgeted total cost plus 50%. Overheads are currently absorbed on a labour hour basis.

Builders Limited thinks that a switch to activity based costing (ABC) to absorb overheads would reduce the cost associated to GC and hence make them more competitive. You are provided with the following data:

Overhead category           Annual overheads             Activity driver          Total number of Activities per year

Supervisors                         90,000                             Site visits                  500
Planners                           70,000                          Planning documents             250
Property related              240,000                             Labour hours                   40,000
Total 400,000

A typical GC costs €3,500 in materials and takes 300 labour hours to complete. A GC requires only one site visit by a supervisor and needs only one planning document to be raised. The typical EX costs €8,000 in materials and takes 500 hours to complete. An EX requires six site visits and five planning documents. In all cases labour is paid €15 per hour.

Required:

Problem (a) Calculate the cost and the quoted price of a GC and of an EX using labour hours to absorb the overheads.

Problem (b) Calculate the cost and the quoted price of a GC and of an EX using ABC to absorb the overheads.

Problem (c) Assuming that the cost of a GC falls by nearly 7% and the price of an EX rises by about 2% as a result of the change to ABC, suggest possible pricing strategies for the two products that Builders Limited sells and suggest two reasons other than high prices for the current poor sales of the GC.

Reference no: EM132960270

Questions Cloud

Where the product is built directly from raw materials : A production environment where the product is built directly from raw materials and components in response to a specific customer order is?
Which is the number of units that has to be produced : The selling price for the finished product is $50. Which of the following is the number of units that has to be produced and sold to break even?
What the estimated inventory on May : Inventory January 1, 2021, $350,000; sales and purchases from January 1, 2021, to May 1, 2021, $1,190,000 and $875,000, What the estimated inventory on May
What is the purpose of holding inventory : What is the purpose of holding inventory? Name several types of inventory and describe their purpose. What are the major assumptions in the EOQ model?
Calculate the cost and the quoted price of a gc : Builders Limited is a building business, Calculate the cost and the quoted price of a GC and of an EX using labour hours to absorb the overheads.
Calculate the value of Camberwell current assets : A junior analyst at Camberwell Corp. has jumbled the items on its balance sheet. Calculate the value of Camberwell current assets
Why must business owners be educated on federal trade : Provide an example of when a deceptive practice has been used in business and the consequence(s) for the deceptive practice.
What amount of gain or loss on the sale would be shown : The balance in the Accumulated Depreciation account was $25,000. What amount of gain or loss on the sale would be shown in the income statement
What impact does consumer behavior in the areas have : In today's world, many people use the Internet, smartphones, and social media. What impact does consumer behavior in these areas have on marketing strategies?

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Which is less emphatic

Which is less emphatic? Profits in beauty care products dropped 15 percent last quarter. One division's profits decreased last quarter.

  Compute the east division residual income for last year

Compute the East division's residual income for last year, also compute the residual income as it would appear if the company performed the same as last year

  Prepare journal entry to close the manufacturing overhead

Prepare journal entry to close the manufacturing overhead account to cost of goods sold. What caused the over-applied or under-applied overhead

  Which compensation would be reported as

Which Compensation would be reported as? Ulia Chen is paid $10 an hour for straight-time and $15 an hour for overtime. One week she worked 42 hours

  Which product or products should be sold at spilt-off point

Which product or products should be sold at the spilt-off point, and which product or products should be processed further? Show computations.

  What is cost of goods sold using variable costing

During the year, Canarie produces 51,900 snow shovels and sells 46,500 snow shovels. What is cost of goods sold using variable costing

  Journalize sandys withdrawal from the partnership

Journalize the asset revaluations and journalize Sandys withdrawal from the partnership.

  You have recently hired a new assistant susan thompson who

you have recently hired a new assistant susan thompson who previously worked in a financial accounting office preparing

  Determine the denominators to be used in the calculation

Determine the denominators to be used in the calculations of cost per equivalent unit for materials and conversion costs.

  Make an expected cash collection budget for the month

The LePann Company has started,Make an expected cash collection budget for the month of July, August, September and for the quarter

  Journalize the incurrence of the labor costs

Journalize the incurrence of the labor costs and the assignment of direct labor to production, assuming a standard cost system is used.

  Determine the indirect labor support costs

Determine the per cent of unused indirect labour compared to available indirect labour hours. Draw conclusions from this analysis.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd