Calculate the cost and schedule variances

Assignment Help Basic Computer Science
Reference no: EM13769795

Question 1. The following information is extracted from a project to develop a state-of-the-art alternative power energy storage device.

Activity Duration Predecessors Resources

A 4 days -- 1 research engineer

B 3 days A 1 marketing specialist

C 5 days A 1 design engineer

D 3 days A 1 design engineer

E 3 days B 1 prototype builder

F 2 days D 1 test engineer

The owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split.

(a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources are involved, and the quantity required.

(b) Given the owner's stipulation regarding project continuity and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration?

Question 2. The following data were obtained from an information systems project to upgrade and expand a local area network.

Activity Duration Predecessors Task Budget

A 3 days --- $4,920

B 6 days --- $7,680

C 3 days A $15,140

D 2 days B $4,980

E 3 days B $5,630

F 2 days C and D $2,270

At the end of Day 7, the status of the project is as follows.

Activity % Complete Actual Cost

A 100% $4,200

B 100% $8,740

C 100% $18,250

D 65% $2,600

E 10% $560

F 0% $0

(a) Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E.

(b) As project manager, write a brief summary of the status of the project at this time.

Question 3. You are project manager for three different projects.

Project A: This project is in the execution stage of the project. It is behind schedule by 6 weeks; it was scheduled to be completed in 10 weeks. The sponsor is desperate to accomplish something on this project. The budget is limited to the original amount, and all soft predecessors have already been removed.

Project B: This project is behind schedule by 10 weeks. It was to have been completed in 2 months. The sponsor has additional funds to help complete the project on time if needed but does not want to increase risk to the project.

Project C: This project is scheduled to take 18 weeks to complete. You are in the planning stage of the project. You need to reduce the schedule for this project by 5 weeks. This project has a number of predecessors that were created by the project team's preference. The sponsor insists on having all the work done on time without unduly increasing risk or costs to the project.

For each of the project above, choose an appropriate schedule compression technique. Explain your choice.

Reference no: EM13769795

Questions Cloud

Discuss similarities anof two characte in given article : discuss similarities and differences of two characters. Compare and contrast essay about Don Anselmo from Juan A. A. Sedillo's "The Gentleman of Río en Medio" and Mrs. Higgins from Morley Callaghan's "All the Years of Her Life."
Create one z-specification for system : Create one (1) short Z-specification for this system using Visio or an equivalent such as Dia. Note: The graphically depicted solution is not included in the required page length.
Matrix of an irreducible recurrent markov chain : Suppose P = ? Pij ? is the transition probability matrix of an irreducible recurrent Markov chain {Xn}. Use the supermartingale convergence theorem (see Remark 5.1) to show that every nonnegative solution y={y(i)} to the system of inequalities , (MIS..
Hazards chemical-polymeric or explosive material : Describe an incident (fire, spill, explosion, etc) you have experienced (or research one on the Internet, professional journal, or scientific magazine article) that involved a polymeric or explosive material(s) and required mitigation.
Calculate the cost and schedule variances : Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E.(b) As project manager, write a brief summary of the status of the project at this time.
Advantages and disadvantages of an investigative task force : What are the advantages and disadvantages of an investigative task force? Who, or what entities, should be involved in the decision to create an investigative task force? Assuming, on balance, that you favor a task force approach, what difficulties d..
Presto printing company sales for the month : Question 1:  Find the mean, median and mode of the following:  Presto Printing Company sales for the month of February.  (NOTE: The company is closed on Sundays.)
What does a woman''s appearance say about her personality : What does a woman's appearance say about her personality or worth? What does a man's appearance say about his personality or worth?
Determine the profile of the investor : Determine the profile of the investor for which this company may be a fit, relative to that potential investor's investment strategy. Provide support for your rationale.

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Identifies the cost of computer

identifies the cost of computer components to configure a computer system (including all peripheral devices where needed) for use in one of the following four situations:

  Input devices

Compare how the gestures data is generated and represented for interpretation in each of the following input devices. In your comparison, consider the data formats (radio waves, electrical signal, sound, etc.), device drivers, operating systems suppo..

  Cores on computer systems

Assignment : Cores on Computer Systems:  Differentiate between multiprocessor systems and many-core systems in terms of power efficiency, cost benefit analysis, instructions processing efficiency, and packaging form factors.

  Prepare an annual budget in an excel spreadsheet

Prepare working solutions in Excel that will manage the annual budget

  Write a research paper in relation to a software design

Research paper in relation to a Software Design related topic

  Describe the forest, domain, ou, and trust configuration

Describe the forest, domain, OU, and trust configuration for Bluesky. Include a chart or diagram of the current configuration. Currently Bluesky has a single domain and default OU structure.

  Construct a truth table for the boolean expression

Construct a truth table for the Boolean expressions ABC + A'B'C' ABC + AB'C' + A'B'C' A(BC' + B'C)

  Evaluate the cost of materials

Evaluate the cost of materials

  The marie simulator

Depending on how comfortable you are with using the MARIE simulator after reading

  What is the main advantage of using master pages

What is the main advantage of using master pages. Explain the purpose and advantage of using styles.

  Describe the three fundamental models of distributed systems

Explain the two approaches to packet delivery by the network layer in Distributed Systems. Describe the three fundamental models of Distributed Systems

  Distinguish between caching and buffering

Distinguish between caching and buffering The failure model defines the ways in which failure may occur in order to provide an understanding of the effects of failure. Give one type of failure with a brief description of the failure

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd