Beck Manufacturing Al Beck, president of Beck manufacturing, wants to determine the capacity of his facil- ity, which produces steering gears for auto manufacturers. He has asked you to sort through the data and determine the capacity of the system and how that capacity may be increased. The operation is a product layout that produces large numbers of nearly iden- tical products. The process includes milling, grinding, boring, drilling, and assembling, in that order. Each finished product requires one operation on each type of machine. For example, each finished part is processed on one of the five milling machines, one of the seven grinding machines, etc.
The facility runs two 8-hour shifts per day, with a third shift for maintenance. The indus- trial engineering department has provided you with the following data on present opera- tions. In addition, you have been told that assembly operations, while not unlimited, can be easily changed to meet the need.
Operations Number of Machines run time per piece
Milling 5 2
Grinding 7 3
Boring 3 1
Drilling 6 2.5
- Calculate the capacity of each machine center and the capacity of the system.
- Analyze where the focus of the company's efforts should be if Beck wants to expand capacity. Determine how much extra capacity he can get without causing another operation to become the bottleneck.
- Suggest ways Beck can expand capacity without purchasing new equipment.
Your paper should be in paragraph form (avoid the use of bullet points) and supported with the concepts outlined as in the text with additional scholarly sources
Provide a description of the project
: Provide a description of the project to your instructor. Outline how the project you choose meets the criteria found in the course project description. The more detail you provide, the better your instructor can determine whether or not your proje..
|
Sap and petrotrin overall enterprise
: How has PMMM brought success to both SAP and Petrotrin's overall enterprise? Use current financial, operational, and strategic news to support the article details for either SAP or Petrotrin to describe their recent results.
|
Inputs for the productivity improvements
: Analyze the trade-offs between inputs for the productivity improvements. Analyze the advantages and disadvantages of global sourcing versus producing in the U.S.
|
What is the system capacity
: What is the system capacity, and which is the bottleneck department? How much slack (unused capacity) is available in other departments?
|
Calculate the capacity of each machine center
: Calculate the capacity of each machine center and the capacity of the system. Analyze where the focus of the company's efforts should be if Beck wants to expand capacity. Determine how much extra capacity he can get without causing another operatio..
|
Impact of an individual personality on work performance
: Explain the impact of an individual's personality on work performance. Identify at least 3 strategies an organization can use to maximize the contribution of individuals.
|
Write the nuclear equation for decay
: Write the nuclear equation for decay - Calculate the binding energy per nucleon and How many nuclei are initial present in a 25.0 mg sample?
|
Complete development of a relational database
: Complete development of a relational database. You are to do the following: Use Visio to create the appropriate diagrams. Create a script named mdbXXX.sql (where XXX are your initials) that Create the tables in 3NF needed to implement your DB schema
|
Examine the relationship between negotiation
: The purpose of this assignment is to examine the relationship between negotiation, ethics, and effective leadership.
|