Reference no: EM131066033
Complete the following problems and submit your answers.
1. You are managing a project with a budgeted cost of $900,000. The project is to be completed in 9 months. After a month you have completed 10% of the project at a total expense of $100,000. The planned completion should have been 15%. Calculate the Budget at Completion (BAC), Actual Cost (AC), Planned Value (PV), Earned Value (EV), Cost Performance Index (CPI) and Schedule Performance Index (SPI) for the project. Show your work. Provide an interpretation on where the project stands in terms of budget and schedule.
2. You are managing a software development project. The project is expected to be completed in 8 months at a cost of $10,000 per month. After 2 months, you realize that the project is 30 percent completed at a cost of $40,000. You need to determine whether the project is on-time and on-budget after 2 months. Calculate the Budget at Completion (BAC), Actual Cost (AC), Planned Value (PV), Earned Value (EV), Cost Performance Index (CPI) and Schedule Performance Index (SPI) for the project. Show your work. Provide an interpretation on where the project stands in terms of budget and schedule.
3. You have been hired to build 10 model train sets, all identical. Each train set is budgeted at $3000. You have scheduled 12 months to complete the project. At the end of 9 months you have 6 train sets complete and have spent $20,000. Calculate the Budget at Completion (BAC), Actual Cost (AC), Planned Value (PV), Earned Value (EV), Cost Performance Index (CPI) and Schedule Performance Index (SPI) for the project. Show your work. Provide an interpretation on where the project stands in terms of budget and schedule.
What is the percentage of reduction in price
: Business Skills - II (BLB10115-4) - Business Maths Assignment - Find the expected blood pressure of a person who is 49 years old and What is the percentage of reduction in price?
|
Write a vector equation that is equivalent to the system
: In write a vector equation that is equivalent to the given system of equations.
|
State opinion on whether or not you think fema belong in dhs
: Use this forum to state your opinion on whether or not you think FEMA belongs in DHS, or whether it should be returned to Cabinet-level status, and support your answer with examples (hypothetical or actual).
|
A nuclear power plant in another country
: If similar explosions had occurred at a nuclear power plant in another country, do you think the workers there would have stayed on the job? Why or why not?
|
Calculate the budget at completion and actual cost
: You have scheduled 12 months to complete the project. At the end of 9 months you have 6 train sets complete and have spent $20,000. Calculate the Budget at Completion (BAC), Actual Cost (AC), Planned Value (PV), Earned Value (EV), Cost Performan..
|
The first entry in the product ax is a sum of products
: The first entry in the product Ax is a sum of products.
|
Write an introduction of genotype and phenotype
: We did an experiment to determine if we had a strong taster gene or weak taster gene or no taster gene so, write an introduction with appropriate title about- broader context, TAS2R38 (GENE and protein and Genotype and phenotype
|
Depict indonesias history of being impacted by globalization
: Describe Indonesia's history of impacting/being impacted by globalization; companies from the country that have/have had a presence in the global economy.
|
When managing project trade-offs
: When managing project trade-offs, it is important to understand the root cause of the conflict, and why the need for trade-offs exists. Project managers must carefully evaluate information about the problems that are occurring in their project. As we..
|