Problem One - PLANT-WIDE RATE AND ACTIVITY-BASED COSTING

The comptroller for Douglas Inc. has established the following activity cost pools and cost drivers.

Activity Cost Pool Cost

Budgeted Overhead Cost Driver

Budgeted Level for Cost Driver

Machine setups

$200,000

Number of setups - 160

Materials handling

100,000

Weighted of material - 50,000 kilograms

Waste control

50,000

Weighted of chemicals - 10,000 kilograms

Quality control

75,000

Number of inspection - 300

Other overhead costs

200,000

Machine hours - 20,000

Each order must be a minimum of 1,000 boxes of film chemicals.

The production requirements for each minimum order are as follows:

Machine setups - 5 setups

Material handling - 1,500 kilograms

Waste Control - 200 kilograms

Quality Control - 5 inspections

Other Overhead Costs - 500 machine hours

Required:

1. Calculate the overhead that should be assigned to each minimum order of film chemicals using the above data.

2. Calculate the overhead that should be assigned to each minimum order of film chemicals if Douglas decides to use a single predetermined overhead rate based on machine hours.

Problem Two - PLANT-WIDE RATE AND ACTIVITY-BASED COSTING

Hood Manufacturing Inc. has four categories of overhead. The expected overhead costs for each of the categories for the next year are as follows:

 

Cost

Cost Driver

Expected Activity

Maintenance

$510,000

Machine hours

60,000

Materials handling

250,000

Materials moves

20,000

Setups

60,000

Setups

3,000

Inspection

21,000

Inspection

12,000

Currently, the company applies overhead using a predetermined overhead rate based upon budgeted direct labour hours of 100,000.

The company has been asked to submit a bid on a proposed job. Usuallybids are based upon full manufacturing costs plus a percentage of 10 percent.

Estimates for the proposed job are as follows:

Direct materials - $30,000

Direct labour - $24,000

Number of direct labour hours - 8,000

Number of material moves - 100

Number of inspections - 120

Number of setups - 24

Number of machine hours - 4,000

Required:

1. If the company used activity-based cost drivers to assign overhead, calculate the bid price of the proposed job.

2. If the company used direct labour hours as the cost driver, calculate the bid price of the proposed job.

Problem Three - NON-VALUE-ADDED COSTS, ACTIVITY COSTS, ACTIVITY COST REDUCTION

BobDaly, vice president of Dwan Company (a producer of a variety of plastic products), has been supervising the implementation of an ABC management system. One ofBob's objectives is to improve process efficiency by improving the activities that define the processes. To illustrate the potential of the new system to the president, Bob has decided to focus on two processes: production and customer service.

Within each process, one activity will be selected for improvement: materials usage for production and sustaining engineering for customer service (sustaining engineers are responsible for redesigning products based on customer needs and feedback). Value- added standards are identified for each activity (the level of efficiency so that no waste exists). For materials usage, the value-added standard calls for six kilograms per unit of output (although the plastic products differ in shape and function, their size-as measured by weight-is uniform). The value-added standard is based on the elimination of all waste due to defective moulds. The standard price of materials is $5 per kilogram.

For sustaining engineering, the standard is 58 percent of current practical activity capacity. This standard is based on the fact that about 42 percent of the complaints have to do with design features that could have been avoided or anticipated by the company.

Current practical capacity (at the end of 2013) is defined by the following requirements: 6,000 engineering hours for each product group that has been on the market or in development for five years or less and 2,400 hours per product group of more than five years. Four product groups have less than five years' experience, and 10 product groups have more. Each of the 24 engineers is paid a salary of $60,000. Each engineer can provide 2,000 hours of service per year. No other significant costs are incurred for the engineering activity.

Actual materials usage for 2014 was 25 percent above the level called for by the Value-added standard; engineering usage was 46,000 hours. A total of 80,000 units of output were produced. Bob and the operational managers have selected some improvement measures that promise to reduce non-value-added activity usage by 40 percent in 2015. Selected actual results achieved for 2015 are as follows:

Units produced - 80,000

Materials used - 584,800

Engineering hours - 35,400

The actual prices paid for materials and engineering hours are identical to the standard or budgeted prices.

Required:

1. For 2014, calculate the non-value-added usage and costs for materials usage and sustaining engineering.

2. Using the budgeted improvements, calculate the expected activity usage levels for 2015. Now, calculate the 2015 usage variances (the difference between the expected and actual values), expressed in both physical and financial measures, for materials and engineering. Comment on the company's ability to achieve its targeted reductions. In particular, discuss what measures the company must take to capture any realized reductions in resource usage.

Reference no: EM131589403

Questions Cloud

Discuss and evaluate the huntington theme : Discussion: Modern Political Analysis- Discuss and evaluate the Huntington theme that we are in a time period of clashes of civilizations?
What type of leadership will work best to develop a team : This paper must be in APA format including title, abstract, and reference page. this paper should be 800 words, and should be written on.
How would you advise a student or family who are concerned : How would you advise a student or family who are concerned about the influence of testing in college admission?
Exchange rate between the us dollar : Assume that the exchange rate between the U.S. dollar ($) and the Mexican peso (P) is pegged at ER=$1/P4.
Calculate the bid price of the proposed job : If the company used activity-based cost drivers to assign overhead, calculate the bid price of the proposed job
Create a semiannual production plan using notional demand : Create a semiannual production plan using notional demand and inventory. Estimate the labor hours consumed.
Explain specific examples to support your explanation : Explain specific examples to support your explanation. Examine specific arguments used by the Justices of Supreme Court in majority and dissenting opinions.
Would it save money for the state to revamp programs : In these stressful times, many state agencies have had to scale back on their programs. One of the most important departments that would deal with future.
Explore the employers section : Explore the Employers section. Based on the information found here, create an apprenticeship proposal for position in company you work for or wish to work for.

Reviews

Write a Review

Accounting Basics Questions & Answers

  For apparel manufacturer abercrombie and fitch

For apparel manufacturer Abercrombie & Fitch, Inc., classify each of the following costs as either a product cost or a period cost:

  What circumstances should brandt company

Brandt Company ships merchandise to England Corporation on December 30. The merchandise reaches the buyer on January

  Adjusted basis for partnership interest basics

During the first year of partnership operations, the following events occurred: the partnership had a net taxable income of $10,000; Michelle received a distribution of $8,000 cash from the partnership; and Michelle had a 50% share in the partners..

  Record leases from both the lessor and lessee perspective

EXPLAIN HOW LEASES ARE USED BY COMPANIES and advantages of this financial arrangement. DISTINGUISH between the different classifications of leases. Record leases from both the lessor and lessee perspective.

  Cash book overdraft balance

While preparing Bank Reconciliation Statements will you add or deduct the following to or from the Cash Book overdraft balance?

  Components of the accounting equation

Components of the Accounting Equation - The financial condition of Greyco Inc. is expressed in the following accounting equation

  Prepare the revised balance sheets

Branford's business is growing rapidly, and the company needs to expand its manufacturing facilities. This expansion will require the company to obtain an additional $1,000,000 in cash. Prepare the revised balance sheets that would result under eac..

  What is the net effect of these transactions in the

the following transactions apply to x companysold merchandise for cash2119paid wages3377purchased new equipment for

  The estimated litigation expense of 1500000 will be

mathis co. at the end of 2012 its first year of operations prepared a reconciliation between pretax financial income

  Determining data for year operations

The pickle department of a major food manufacturer has an overhead rate of $5 per direct-labor hour, based on expected variable overhead of $150,000 per year, expected fixed overhead of $350,000 per year, and expected direct-labor hours of 100,000..

  Compute the items for rattlesnake corporation

Compute the following items for Rattlesnake Corporation. Show supporting computations. Round all calculations to the nearest whole dollar.

  Sales and production budgets 8-12 the marketing department

complete the following three exercises and submit to your instructor. be sure to show your work for calculations to

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd