Reference no: EM132784159
During 2020, ABC Construction Co. began a construction job with a contract price of S2.8 million. The job was completed in 2022. The data below is available:
2020 2021 2022
Costs Incurred to Date $1,000,000 $1,600,000 $1,800,000
Estimated Costs to Complete $1,100,000 $400,000 $0
Billirtp to Date $1,050,000 $ 2,150,000 $2,800,000
Collections to Date $900,000 $2,100,000 $2,800,000
- ABC Construction Co. follows IFRS and therefore, uses the percentage-of-completion method to account for its Tong-terra contracts.
Required:
Round all currency to 2 decimal places. Round all percentages to 7 decimal places.
Problem 1: Determine the percentage complete for the end of 2020, 2021 and 2022.
Problem 2: Calculate the amount of gross profit to the recognized each year assuming the percentage-of-completion method is used.