A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.
Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)
What are recent examples of unethical business decisions that have had a large impact on society? Why do you think the capstone course for the MBA program has a heavy emphasis on ethical decision making?
Present at least 3 data collection methods for organizational diagnosis. Discuss Elucidate how data collecting is used in the opening stages of a change process.
Your firm is considering to open a new factory via direct investment in Latin America and management is evaluating the specific country locations for this project.
The same bakery also makes gourmet chocolate-chip cookies by the dozen to sell to local grocers. The bakery is contracted to supply 30 dozen cookies a day to the grocers.
Discuss transportation and logistics management policy. Illustrate what impact does policy (local, state, and/or federal) have on transportation.
describe whether you relied on external or internal sources of information to help you make every decision also whether you think you were more linear or nonlinear in describe how you processed which information.
Flex Electronics Gadget, Inc. produces 4 types of PCB (printed circuit boards), each of which requires different combination of treatment. There are 7 treatment station.
Pick a company. Describe the switching costs that the company would incur if it began to phase out its current suppliers and pick new suppliers.
what is the difference between a causal model and a time-series model? Give an example of when each would be used. What are some of the problems and draw backs of the moving average forecasting model?
Elucidate how are organizations similar to living things. Illustrate what are organizational behaviour model also its focus. Why is it important to understand organizational behaviour.
Two-hour program involved distance learning also was broadcast from sears training facility to 50 salespersons at 10 store locations in United States. Illustrate what is return on investment from this program.
Sample No. of Incorrect Bills 1 6 2 5 3 11 4 4 5 0 6 5 7 3 8 4 9 7 10 2 a) Determine the value of p-bar, the mean factor defective. Then determine the control limits for the p-chart using a 99.73% confidence level.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd