Calculate minimum costs, times, and cost schedules

Assignment Help Project Management
Reference no: EM1343495

Calculate minimum costs, times, and cost schedules

Consider the following table of crash times and costs for the above project.

Activity
normal time crash time normal cost crash cost

A 3 1 9000 17000
B 6 3 20000 40000
C 2 1 5000 10000
D 5 3 18000 24000
E 4 3 15000 18500
F 3 1 30000 39000
G 9 4 80000 98000
H 3 2 10000 20000

In the above table normal and crash times are in weeks. Costs are in dollars and represent the costs associated with the job in the specified period. For instance, Phase A will normally take 3 weeks and cost $9000, OR $3000 PER WEEK. To crash the job to one week, the total cost will be $17000 for the week, thus it will cost $4000 for each week crashed.

a. What is the minimum cost to crash the project one (1) week? What activity will be crashed?

b. What is the least amount of time the project can take if fully crashed? What will the project cost fully crashed?

c. Develop a cost schedule for total project cost from finishing in the normal time to maximum crashing, ie. cost to finish in normal time , cost if crashed one week, cost if crashed two weeks, etc. to minimum time to complete.

Reference no: EM1343495

Questions Cloud

To develop a visual basic console application : The aim of the assessment is to develop a Visual Basic console application that performs a number of mathematical functions. The mathematics package will be menu driven, i.e. a number of options will be displayed, and the user will be able to input w..
What is a project life cycle : Describe a project that you have worked on, either in personal life or in business, and what was good or bad about that project.
What are pm triple constraints : What are PM triple constraints assume you have just completed a project and met all project goals except cost
Project planning, risk and time management : Project management activities and project development activities and try to explore what can be done about that.
Calculate minimum costs, times, and cost schedules : Calculate minimum costs, times, and cost schedules - What is the minimum cost to crash the project one week and What activity will be crashed
Limitation of research and project : Many will argue that it is considered a good practice to acknowledge the limitation of your research and project
How did the virginia plan : How did the Virginia Plan, the New Jersey Plan, the Great Compromise, and the Three-Fifths Compromise lead our current form of Congress?
Case of a member of a manager-managed llc : Case of a member of a manager-managed LLC - Eric is a member of a manager-managed LLC but is not a manager. This LLC invests in real estate and manages it as rental property in a college town.
Design and implement a library system : Design and implement a library system that does the following: ? Takes details of a student/library users: first name, last name, other names, user ID number, and nationality.

Reviews

Write a Review

Project Management Questions & Answers

  Preparing a project to lay fiber optic cable

You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable.

  Monitor and control project progress

Monitoring and Controlling Project Progress and what are some of the ways that a project manager can use budgeting plans to track and compare actual data on project progress?

  Explain meaning of contingency fee

Explain meaning of contingency fee.

  Project selection

Which one of the four projects should Lakeway Train Co. choose based on the same criteria of using the coefficient of variation?

  Improving quality can lead to reduced costs

Explain how improving quality can lead to reduced costs.

  Project acceptance

Project Acceptance - Aerospace Dynamics will invest $110,000 in a project that will produce the following cash flows.

  Question about financial systems

Explain what are the economic functions financial intermediaries perform and what is the role of broker in the financial market

  Incentives to invest

What happens if the country you chose provides incentives to invest? Now that your organization is profitable, the country is taking incentives back

  Mid-level employee for a procurement office

Seeking a mid-level employee for a procurement office - the supervisor of an eight-person procurement office for a manufacturing company.

  Computing after-tax net cash flow of project

What is the after-tax net cash flow in the thirteenth year of the project?

  Developing a budget number around project schedule

Develop a budget number around our project schedule, be sure to include your constraints and the alternatives you can use to overcome these constraints.

  What can project manager do in case like this

Who may not have decision-making authority but are "warm bodies" just sent to sit in on meetings and what can the project manager do in this case?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd