Reference no: EM132833457
Question - During July, the following costs were incurred:
Materials (30,000 units) $24,900
Labour and overheads $20,075
At the beginning of July, there were 15,000 units of work in progress valued as follows:
Materials (100% complete) $9,000
Labour and overheads (40% complete) $1,250
At the end of July, there were 5,000 units of work-in-progress. They were 100% complete for materials and 50% complete for labour and overheads.
Required - Using both FIFO approach and Weighted Average approach:
(a) Calculate how many units were completed during July.
(b) Calculate the cost per unit.
(c) Calculate value the finished items and the closing work-in-progress.
(d) Create a Process Account. (Note: assume no losses).