Calculate how many days are needed to complete an activity

Assignment Help Project Management
Reference no: EM13854373

1. Problem statement and aims of the project

Why do you need to do this project? Give some background information and mention the feasibility study. Remember the lead up to the feasibility study (from the clients' perspective) is the formalising of the project with the project charter. The project charter outlines the purpose of the project and what it is meant to achieve. Also called terms of reference, or project mission.

2. Scheduling (time management)

The following practical steps can be taken to schedule a project:

♦ Identify the activities. Divide the project into logical activities. Each activity is specialised and may have to wait for a preceding activity to be completed before being carried out. It is advisable to assign activities to responsible people at this stage.

♦ Plan starting and completion dates. Plan the starting dates of each activity. Note that some activities can start immediately because they don't depend on the completion of preceding activities. Activities may therefore overlap. The starting dates of other activities may depend on the completion dates of preceding activities.

♦ Estimate the duration of each activity. Calculate how many days per week are needed to complete an activity. Duration may also be calculated in hours for a more accurate picture.

♦ Modify the schedule as necessary. Once the various interest groups have been consulted, the provisional schedule may need to be modified.

♦ Prepare the schedule. The Gantt chart can now be drawn (see example of Gantt chart). As the project progresses, its actual state should be indicated in the centre of the chart. The process needs to be monitored constantly to take corrective steps if there are any deviations from the planned chart.

♦ Distribute the schedule to all team members and the community (if you do a community project). Once the schedule has been completed and the Gantt chart drawn, they must be distributed to all team members. They could also be distributed among the community or to heads of department of the institution to ensure transparency. The Gantt chart is a useful way of giving regular feedback on the progress of the project to the community of policy-making body of the institution.

Attachment:- Project.pdf

Reference no: EM13854373

Questions Cloud

How independent models of inventory management are utilized : Be sure to do an analysis of how independent and dependent models of inventory management are utilized in the firm's decision making process and how it alters them to respond to sudden changes in the market demand for its product.
Different ways that media works : Each of the previous assignments in this class has asked you to critically engage with media - by examining your own personal relationship, outside representations, or capitalist structures - and think about the different ways that media works to ..
Determining the atmospheric density : A tank of volume V. is filled initially with air at atmospheric density pa,. Beginning at t = 0, a pump delivers to the tank a mixture  of air and water.
Prime brokerage customers for use as working capital : Prime brokerage accounts were moved from Bear Stearns during the week of 2010. This was part of the run. These accounts were closed so Bear no longer had access to the funds deposited by their prime brokerage customers for use as working capital. tru..
Calculate how many days are needed to complete an activity : Calculate how many days per week are needed to complete an activity. Duration may also be calculated in hours for a more accurate picture.
Drafts of the external and internal environmental analysis : Identify one important concept, research finding, theory, or idea in strategy that you learned while completing this weeks work. Why do you believe that this concept, research finding, theory, or idea in strategy is important
What was the firm''s 2012 operating cash flow, or ocf : The 2011 balance sheet of Anna's Tennis Shop, Inc., showed long-term debt of $5.5 million, and the 2012 balance sheet showed long-term debt of $5.75 million. The 2012 income statement showed an interest expense of $180,000. The 2011 balance sheet of ..
Dependency diagram reflects a table that is in : dependency diagram reflects a table that is in
Exxon is evaluating an oil well : Question 2:Exxon is evaluating an oil well that will produce oil for two years. In year 1, the company plans to produce 100,000 barrels of oil, and the production cost will be $20 per barrel. In year 2, it plans to produce 50,000 barrels of oil, but ..

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd