Reference no: EM13784016
The total costs of a proposed project consist of fabrication costs and installation costs. Each cost is uncertain. Fabrication costs Probability Installation costs Probability $MM % $MM % 10 40% 5 25% 20 50% 10 60% 50 10% 30 15% 3.1. Assume that there is no correlation between fabrication and installation costs.
Calculate and tabulate the probability distribution of the total costs of the project.
1. What are
- the most likely total costs,
- the approximate 90th, 50th and 10th percentiles (the "P90", the "P50" and the "P10") from the "more than" cumulative distribution,
- the mean total costs and
- the standard deviation of the total costs?
2. Assuming that you had to pick only one estimate of the total costs, which single measure would you use? Why?
3. Recalculate and tabulate the probability distribution of the total costs assuming perfect positive correlation between the fabrication costs and installation costs.Calculate the standard deviation of the total costs.
In answering question 3, assume that perfect positive correlation means that when the fabrication costs are low, medium and high, the installation costs are correspondingly low, medium and high.
In addition, assume
(a) that low fabrication costs and installation costs have a 40% probability,
(b) that medium fabrication costs and installation costs have a 50% probability and
(c) that high fabrication costs and installation costs have a 10% probability.
4. Recalculate and tabulate the probability distribution of the total costs assuming perfect negative correlation between the fabrication costs and installation costs. Calculate the standard deviation of the total costs.
In answering question 4, assume that perfect negative correlation means that when the fabrication costs are low, medium and high, the installation costs are correspondingly high, medium and low.
In addition, assume
(a) that the low fabrication costs and high installation costs case have a 40% probability,
(b) that the medium fabrication costs and medium installation costs case have a 50% probability and
(c) that high fabrication costs and low installation costs case have a 10% probability.
5. Comment on the standard deviations calculated in questions 1, 3 and 4. Why are they different?
6. Assume that you have continuous probability distributions of cost estimates of the components of a project. Each of the distributions is log-normal.
- What is the difference between the sum of the "P90"s from each of the "more than" distributions and the "P90" of the statistical sum of the distributions?
- What is the difference between the sum of the "P50"s from each of the "more than" distributions and the "P50" of the statistical sum of the distributions?
- What is the difference between the sum of the "P10"s from each of the "more than" distributions and the "P10" of the statistical sum of the distributions? Give reasons for the differences.
Find the probability distribution of the number of times
: The probability that I go to the gym on any given day of the week is 30%. Find the probability distribution of the number of times that I go to the gym over the course of one week (7 days).
|
What is the probablility that the sample mean is less than
: The Diameter of a brand of ping pong balls is approximatley normally distributed with the mean of 1.31 inches and the standard deviation of 0.04 inch a random sample of 16 ping pong balls is selected A) what is the probablility that the sample mean i..
|
A steel company is producing steel for a new contract
: A steel company is producing steel for a new contract. The contract specifies the information in the following table for the steel. MATERIAL MINIMUM MAXIMUM Maganese 2.10% 3.10% Silicon 4.30% 6.30% Carbon 1.05% 2.05% The steel company mixes batches o..
|
A random variable x has mean
: A random variable x has mean -4 and E(X)^2=20. What is the standard deviation of X.
|
Calculate and tabulate the probability distribution of the
: The total costs of a proposed project consist of fabrication costs and installation costs. Each cost is uncertain. Fabrication costs Probability Installation costs Probability $MM % $MM % 10 40% 5 25% 20 50% 10 60% 50 10% 30 15% 3.1. Assume that ther..
|
Continuing to do business with marshall
: Review the Contracts Analysis Case Study prior to answering the questions listed below. Assignment: Write a legal analysis of at least 1,000 words that answers the following questions from both a legal and a spiritual perspective: 1. What should you ..
|
Research from the csu online library and the other sources
: Research from the CSU Online Library and the other sources for the current desktop processors available from both AMD and Intel. Next, provide the requirements for several PC builds (a low cost computer, a mid-range, and a high- performance computer)..
|
Perform a hotelling t2 two sample test
: Perform a Hotelling T2 Two Sample test to determine if a certain drug has any effect in reducing flue-like symptoms. Use alpha = 0.01.
|
What is the cost of the test which will make us indifferent
: We need to acquire a piece of equipment. However, we are uncertain about its reliability. It might need a low, medium or a high number of repairs during its life. The present value ("PV") of the costs of the equipment over its life would be as follow..
|