You are developing a new rocket motor for NASA. The project duration is planned for 20 weeks. The project budget is $40,000 and is planned to be spent on a level bases through out the project. You are at the end of week 10, the accounting department tells you the project has spent $19,500, your project manager tell you that you are 40% of the WBS is complete. Calculate the following;
Actual Cost, Earned Value, Planned Value.
Actual Cost should be $40,000 * 0.40 = $16,000
Planned Value = 40,000
Earned Value = $40,000 - (40,000*0.6) = $16,000
A CU triaxial test with σc = 20 psi is performed on a sand and a deviator stress of 80 psi fails the specimen. Previous tests revealed that the effective friction angle for this sand is 35°. Calculate the pore water pressure at failure.
A radioactive waste from a clinical laboratory contains 0.2 μCi (microcuries) of calcium-45 (45Ca) per liter. The half-life of 45Ca is 152 days.
How do you find the force ratio equation to determine the maximum total load that can be applied to a truss?
If the amount of heat transfer in the HE unit is 2460 kJ per kg of steam, what is the magnitude of shaft work obtained from the turbine in kW?
Calculate the numbers of married men, single men, married women and single women. Print these numbers on a student summary report. If any single men are over 30 years of age, print their names and ages on a separate eligible bachelors report.
Calculate the elongation of a steel bar 4 feet in length and 4 inches in diameter when subjected to a force of 2.5 kips. Assume that the bar remains in the elastic region with E=30 ksi.
A discharge of 2,200 ft^3/sec flows in a trapezoidal channel at a normal depth of 8.0 ft. The channel has a slope of 0.01, a 12-ft bottom width, and side slopes of 1:1 (H:V). Determine the manning coefficient of channel roughness
What are the basic differences between the AFL as a labor union and the CIO type of union?
What are Engineering Societies based upon the research? List at least 10 discipline specific engineering societies along with their website addresses.
Use modern software tools to analyze a structural system of a building.
Property taxes,insurance and storage will run 5%.What is the owning cost for the dozer?Use the time value method to calculate the depreciated portion of the ownership cost.
what is elastic wave tomography , flat jack, push shear test in masonary?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd