Business process perspective

Assignment Help Operation Management
Reference no: EM131724962

The first Boeing 787 Dreamliner was delivered to Japan's ANA in the third quarter of 2011, more than three years after the initial planned delivery date. Its complicated, uniqure design (including a one-piece fuselage that eliminiated the need for 1,500 aluminim sheets and 50,000 fasteners and reduced the resulting weight of the plane proportionaly) promised both a reduction in out-of-service maintenance time and a 20% increase in fuel economy, but problems with early testing of the new design contributed to the giant project's troubles. Even after those delays, the 787 was grounded in January 2013 because the main battery had problems of overheating and subsequently burning. The problems were finally reported solved in December 2014.

Delivery of Boeing's 787 Dreamliner project was delayed, in part, because of the company's global supply chain network, which was touted to reduce cost and development time. In reality, the network turned out to be a major cause for problems; rather than simply relying on technological know-how, it decided to use collaboration as a competitive tool embedded in a new global supply chain process.

With the Dreamliner project, Boeing not only attempted to created a new aircraft through the innovative design and new material but also radically changed the production process. It built an incredibly complex supply chain involving over 50 partners scattered in 103 locations all over the world. The goal was to reduce both the financial risks involved in a $10 billion-plus project for designing and developing a new aircraft and the new product development cycle time. Boeing tapped the expertise of various firms in different areas such as composite materials, aerodynamics, and IT infrastructure to create a network in which partners' skills complement each other. This changed the basis of competition to skill set rather than the traditional basis of low cost. In addition, this was the first time Boeing had outsourced the production on the two most critical parts of the plane - the wings and the fuselage.

The first sign of problems showed up just six months into the trial production. Engineers discovered unexpected bubbles in the skin of the fuselage during baking of the composite material. This delayed the project a month. Boeing officials insisted that they could make up the time and all things were under control. But next to fail was the test version of the nose section. This time, a problem was found in the software programs, which were designed by various manufacturers. They failed to communicate with each other, leading to a breakdown in the integrated supply chain. Then problems popped up in the integration of electronics. The Dreamliner program entered the danger zone when Boeing declared that it was having trouble getting enough permanent titanium fasteners to hold togeter various parts of the aircraft. The global supply network did not integrate well for Boeing and left it highly dependent on a few suppliers.

The battery problems involved lithium-ion batteries that could not recover from a situation involving a rare but serious internal short circuit that would cause flames to spread from one cell to another. Lithium-ion batteries had not previously been used in an airplane and had not been tested under an assumption of a short circuit.

This case clearly underscores the hazards in relying on an extensive supply chain, failing to expect the worst case with ciritical new parts, and encountering information exchange problems that caused long delays and seriously compromised a company's ability to carry out business as planned. Creating a radically different process can mean encountering unexpected problems. In some cases, it would put a company so far behind its competition that it was doomed to fail. However, in this case, the major competitor to the Dreamliner, the Airbus 380 program, was also using a global supply chain model, and its program was delayed by a couple of years. The result for Boeing was a much-anticipated plane with fuel economy and outstanding design that made the wait worth it. However, because of compromises in design, the Dreamliner holds only up to 250 passengers, compared to the A380, which has a seating capacity between 525 and 853.

PLEASE give full detail discussion answers to the following questions:

1. Why did Boeing adopt the radical change approach for designing and developing the 787 Dreamliner? What were the risks? In your opinion, was it a good move? Defend your choice.

2. Using the SILO perspective versus BUSINESS PROCESS PERSPECTIVE, analyze the Dreamliner program.

3. What are your conclusions about the design of the integrated supply chain? Give some specific ideas about what could have been done to integrate it better.

4. If you were the program manager, what would you have done differently to avoid the problems faced by the Dreamliner program?

Reference no: EM131724962

Questions Cloud

How does project consulting relates to managerial accounting : How does Project Consulting relates to Strategic Marketing? How does Project Consulting relates to Managerial Accounting?
Justified in acting on information acquired in this manner : From an ethical standpoint, do you think the auditors would be justified in acting on information acquired in this manner?
Explain how computer technology may enhance collaboration : Explain how computer technology may enhance collaboration.
Initial brainstormed list for report on stress in workplace : The following is writer's initial brainstormed list for report on stress in workplace. Revise brainstormed list, eliminating repetition-combining related items.
Business process perspective : Using the SILO perspective versus BUSINESS PROCESS PERSPECTIVE, analyze the Dreamliner program.
Describe how public opinion is measured : Describe how public opinion is measured and some of the challenges that arise with polling/ Specifically, discuss what sampling is, why sampling is used,
Describe your product or service-pricing structure : In this Assignment, you will analyze and then describe your product or service, pricing structure, product or service life cycle,
How many orders were placed by customers in each state : How many orders were placed by customers in each state? Use the join facility to answer this question; do not use subqueries.
High risk-high to low risk-low return for lighting company : Name five methods of entry in the order of high risk/high return to low risk/low return for the lighting company.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd