Build out of the new facility

Assignment Help Project Management
Reference no: EM131375912

The Project Case under consideration have the following major Headings:

1. Project Planning

2. Pre-move Activities

3. Moving Activities

4. Post-move Activities

these could be denoted as the Major Tasks.

The tasks that have been identified are:(As Given)
- Decide on new furniture
- office preparation
- kick-off meeting
- set up utilities
- build out of the new facility
- initial planning for overall project
- actual move of existing furniture and files
- installation of new communication equipment, servers, and computers
- pack-out of existing office files, supplies, and material
- Installation of new signs
- Project closeout activities.

These could be denoted as the Sub-Tasks.
Some of the other main activities or tasks that needs to be completed are: (Some Preconditions)
- Relocate the entire office of 200 people to a new office building across town.
- Purchase and installation of items for the new building is part of the project's responsibility.
- Removal of items not being moved and general cleanup of the old office space is outside the scope of this project.
- Moving of all large, heavy items will be outsourced to a professional moving company.
- IT plans to replace all computers and servers with updated technology.
- The move is scheduled for the last week in July.

These could be denoted either as the Master or the sub-sub tasks as per the headings(Hans, 2013).

Some Assumptions:
- The work staring from 1st Feb, 2017
- No Holidays considered
- In a week it is considered to be 5 working days with holidays on Saturdays & Sundays.
- The work duration for each task is considered as per standard timings

However, after clubbing the above Major Tasks, Sub-Tasks, Master or the Sub-sub tasks the Project Schedule along with the WBS numberings could be done.

WBS Sl No

Project Work

Predecessors

Duration (Days)

Start Date

Finish Date

1

Relocate the entire office of 200 people to a new office building across town

 

 

 

 

1.1

Project Planning 

 

 

 

 

1.1.1

Initial planning for overall project

Start

 

 

 

1.1.2

Kick-off meeting

1.1.1

5 Days

1/2/2017

7/2/2017

1.2

Pre-move Activities 

 

 

 

 

1.2.1

Office preparation

1.1.2

10 Days

8/2/2017

21/2/2017

1.2.2

Decide on new furniture

1.2.1

10 Days

22/2/2017

7/3/2017

1.3

Moving Activities 

 

 

 

 

1.3.1

Professional Moving Company Deployed

 

 

 

 

1.3.1.1

Actual move of existing furniture and files

1.2.2

15 Days

8/3/2017

28/3/2017

1.3.1.2

Pack-out of existing office files, supplies, and material

1.3.1.1

15 Days

29/3/2017

18/4/2017

1.4

Post-move Activities 

 

 

 

 

1.4.1

Purchase and installation of items for the new building

 

 

 

 

1.4.1.1

Build out of the new facility

1.3.1.2

10 Days

19/4/2017

2/5/2017

1.4.1.2

Installation of new signs

1.4.1.1

5 Days

3/5/2017

9/5/2017

1.4.1.3

Set up utilities

1.4.1.2

10 Days

10/5/2017

23/5/2017

1.4.2

IT plans to replace all computers and servers with updated technology

 

 

 

 

1.4.2.1

Installation of new communication equipment, servers, and computers

1.4.1.3

15 Days

24/5/2017

13/6/2017

1.4.3

Project closeout activities

1.4.2.1

5 Days

14/6/2017

20/6/2017

Table: Project Schedule & WBS of the Project for relocation, Source: (Hillson, 2003)

Now that you have created the work breakdown structure and received approval to begin scheduling the office move, your manager, Steve Spaniels, would like to review a network diagram and present it to the CEO.

You have worked with your project team to estimate the durations of each of the work packages in the WBS. The following is your current plan:

Work Package

Duration (days)

Predecessors

1) Initial planning

20

 

2) Kick-off meeting

1

 

3) Decide on furniture

25

 

4) Office preparation

20

 

5) Actual move

5

 

6) Build out of new facility

45

 

7) Install of furniture/servers/equipment

10

 

8) Set up utilities

30

 

9) Pack-out existing office

10

 

10) Install new company signs

15

 

11) Closeout activities

5

 

Assignment:

Please review the Network Diagraming section in Chapter 6 of the text (starting on page 201). Create a project network diagram by first identifying the task predecessors (above). Once you have completed the network diagram:

1) Calculate the forward pass and backward pass

2) Calculate activity slack and project float

3) Identify critical path

Journals are private between the student and the instructor. Approach these activities as (a) an opportunity to reflect upon and apply what you learn each week based on the assigned readings, discussions, and activities, and (b) an opportunity to share your knowledge and expertise based on your educational and professional experiences in the past. As a successful professional, you will need good reflective and writing skills. Journal activities offer you the opportunity to further develop these skills. For more information about Blackboard blogs and journals, review these tutorials.

Verified Expert

The paper is about the work breakdown structure and received approval to begin scheduling the office move, the manager, Steve Spaniels, would like to review a network diagram and present it to the CEO. A project network diagram by first identified followed by calculations. It will also help in understanding the work breakdown structure and scheduling activities of project through network diagram and will also include the calculations that estimate various aspects of the project.

Reference no: EM131375912

Questions Cloud

Is bullying more serious now than with previous generations : Do you think this boy's response was appropriate? What consequences should youth who retaliate against bullies face?Is bullying more serious now than with previous generations? Support your answer. What should be done to address the issues that cau..
Was it qualitative or quantitative approach : Think back to a time in your life when you were faced with a critical decision. Describe what your decision was, and the approach you took to making it. Did you use a systematic approach? Was it a qualitative or quantitative approach? What was the ou..
Approaches to public administration paper : This assignment is worth 100 points. Your report is to be prepared as a Word document and transmitted to the instructor as a Dropbox attachment. The entire document is to be 600 to 1,000 words in length.
Create a written report with the given information : Create a written report with the following information for the small business you have selected: Name of business and business owner and Original start-up business opportunity.
Build out of the new facility : Relocate the entire office of 200 people to a new office building across town and purchase and installation of items for the new building is part of the project's responsibility - Relocate the entire office of 200 people to a new office building acro..
Evaluate the relationship between ethics and leadership : Go on to examine and critically evaluate the relationship between ethics, leadership and decision making. In conclusion, reflect critically on how leaders may ensure organisational decisions are made ethically
What is one of main reasons the rooftop unit has to be level : If the rooftop unit is subjected to a corrosive environment, and cannot be installed in an area away from the offending corrosion, what would be a possible alternative?
Linear programming is very common decision tool : Linear programming is very common decision tool used by organizations for a variety of purposes including planning business operations, portfolio optimization, and workforce planning.
Mental disturbance and delinquency : While there is evidence suggesting an association between mental disturbance and delinquency, it was pointed out that there are intervening variables that may account for the association. List and describe these factors. Do you think these factors..

Reviews

len1375912

1/30/2017 1:49:51 AM

Network Diagram Entry clearly describes the process of the network diagram including the forward/backward pass, slack/float, and critical path with specific relevant examples Synthesis Entry shows excellent evidence of synthesis of the module content and exhibits careful consideration of the topic Voice Entry is written in a style that is appealing and appropriate for the intended audience and a consistent voice is evident throughout Writing Entry is free of errors in organization and grammar

Write a Review

Project Management Questions & Answers

  Culture on the role and authority of the project manager

Important information about organization's structure and culture - explain what are the effects of an organization's structure and culture on the role and authority of the project manager?

  Communication and business abroad

Explain what does the Indian business woman need to know about the male executive of this South American Country

  Risk management in any environmentthe text david burt et

risk management in any environmentthe text david burt et al. 2010 discusses risk management in the supply chain area.

  Important information about communication skills

Prepare a proposal to the chief executive officer of Blue Ridge Enterprise, Andrea R. Martinez, outlining this problem and the steps you suggest to help solve the problem.

  Security managementcan you help me get started on this

security managementcan you help me get started on this assignment?1 why is security management more important today

  Describe most effective tone for a claim or complaint letter

hen might persuasion be necessary in messages flowing upward? -  Describe the most effective tone for a claim or complaint letter.

  Computing expected return on project using capm

What is the expected return on the project using CAPM?

  Discussion-managing stakeholders

Discuss ways that you have seen people manage stakeholder engagement in your classroom or work environments. Which approaches seem to work the best?

  Discuss the role of the project manager or team the

research and read an article on recent recipients of the project management institutes project of the year award. write

  Computing the coefficients of variation of project

Which of the following four projects should Mountain Ski Corp. choose? Compute the coefficients of variation to help you make your decision.

  Post tender negotiations

Post Tender Negotiations (PTN) as obvious advantages and disadvantages - debate on PTN and commercially best value

  Part 1come up with a goal calculate constraints and

part 1come up with a goal calculate constraints and formulate a reasonable investment policy statement.part 2select

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd