Build an AoN diagram with forward and backward pass

Assignment Help Project Management
Reference no: EM132340627

Question 1 - You are a project manager who is tasked to produce a driverless truck. To do this, you first need to build and test a prototype of driverless truck in the lab. Below are activities involved to build the truck. Each activity has the duration and its predecessor activities.

Activity

Description

Duration

Predecessor

1

Design

5

N/A

2

Procure prototype parts

8

1

3

Fabricate parts

6

1

4

Assemble prototype

5

2, 3

5

Laboratory test

6

4

6

Field test

8

5

7

Adjust design

5

6

8

Order stock components

5

7

9

Order custom components

10

7

10

Assemble test production unit

10

8, 9

11

Test unit

5

10

12

Document results

3

11

Your next steps are:

a. Build an AoN diagram with forward and backward pass to find the ES, LS, EF, LF and Slack days for each activity listed above. (Note: Assume the first activity starts on day 0).

b. Find the critical path in your AoN diagram and the total duration of the project.

c. Transfer all information from the AoN diagram to MS Project and create a Gantt Chart. (Note: Base your plan on the following guidelines: eight-hour days, seven-day weeks, no holiday breaks, 2nd January is the project start date.).

Instructions: You are to submit all answers in the PDF document (this includes copying and pasting the AoN diagram and any diagrams from MS Project).

Question 2 - Read the Advantage Energy Technology data Centre Migration (Case study 6.1, Chapter 6, pages 203-204) from your textbook and answer the following sub-questions:

a. Generate a priority matrix for AET's system move and provide a justification for your choices.

b. Develop a WBS table for Brian's project. Include duration (days) and predecessors.

c. Develop an AoN diagram with forward and backward pass to find the ES, LS, EF, LF and Slack days for each activity listed above. (Note: Assume the first activity starts on day 0).

d. Use Microsoft Project or some other project management software available to you to develop a schedule for this project. (Note: Base your plan on the following guidelines: eight-hour days, seven-day weeks, no holiday breaks, 1st March is the project start date.).

Question 3 - You have prepared the following schedule for a project in which the key resource is an injection moulding machine. This schedule is contingent on having 3 such machines.

744_figure.png

You receive a call from your partner, Benson, who desperately needs 1 of your injection moulding machines. You tell Benson you would be willing to let him have the machine if you are still able to complete your project in 10 months.

a) Develop a resource schedule and draw a loading chart to see if it is possible to complete the project in 10 months with only 2 machines. Be sure to record the order in which you schedule the activities using scheduling heuristics.

b) Assume that activity 5 requires 2 machines, while all other activities require 1 machine. No splitting of activities is possible. Can you say yes to Benson's request?

Write a paragraph answering the question: "Can you say yes to Benson's request?"

Indicate any assumptions you made and show calculations and justification to clearly indicate how you arrive at your answers.

Question 4 - Assume that you have the following decision-making options:

(1) make the decision on your own with available information,

(2) consult others before making a decision, and

(3) call a meeting and reach a consensus, seeking to arrive at a final decision everyone can agree on.

a) Research and find an example online of two difficult business decisions.

b) Write a paragraph in your own words to describe each decision (1/2 to 1 page total).

c) Write another paragraph for each decision to discuss which approach would you use to make the decision and why (1/2 to 1 page total).

Remember to indicate where your information came from.

Question 5 - a) On day 51 a project has an earned value of $650, an actual cost of $690, and a planned cost of $590. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

b) Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 5 and the end of period 9.

c) From the data you have collected and computed for periods 5 and 9, what information are you prepared to tell the customer about the status of the project at the end of period 9?

Use the following information to help you to produce a report for period 5 and period 9 (see attached file).

Clearly show or explain how you arrived at your answers (simply writing the answer alone is not enough). Make sure that you justify your opinions.

Note - Please make sure, to use Microsoft project for the questions where it is required.

Attachment:- Assignment File - Questions.rar

Reference no: EM132340627

Questions Cloud

Inner city residents have sleep apnea : There is a 3.32% chance that the percent of all inner city residents have sleep apnea differs from 13%.
How do advertisers try to use group influence : How do advertisers try to use group influence? Can you find any specific examples and describe the relevant theory of group behavior and influence
Null and alternative hypothesis for a test : The null and alternative hypothesis for a test are Ho: U = 10.9 and Ha: U does not equal 10.9, respectivly
Determine the probability of a type i error : Please determine the probability of a type I error for the following .65 , .70 , .75 , .80
Build an AoN diagram with forward and backward pass : Build an AoN diagram with forward and backward pass to find the ES, LS, EF, LF and Slack days for each activity listed
Determine the probability of a type i error : Please determine the probability of a type I error for the following .65 , .70 , .75 , .80
Who has more consistent labor hours and why : If one company has an average of 292.2 hours per sq foot with a standard deviation of 141.3654 and another has an average of 350 hours per square foot
How many different ways can the three summer outfits : Sara has eight new summer outfits. She plans to pack three of the new summer outfits in her trip to Tokyo.
How many different ways can the officers be appointed : UMUC Stat Club must appoint a president, a vice president, and a treasurer. There are 10 qualified candidates.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd