Bridge building project in edmonton

Assignment Help Financial Management
Reference no: EM131861506

Roadworthy Inc. is a bridge construction company. It has been contracted on a $75 million bridge building project in Edmonton. The contract terms specified that the company must complete the project within three years, and the company will be paid at the end of each year according to the percentage completion on the bridge. For example, at the end of the first year of construction, the company will be paid 25% x $75 million = $18.75 million, as per the company’s submitted bid, which indicated the following completion schedule:

Year 1: 25% completion

Year 2: 75% completion

Year 3: 100% completion

The contract terms also specified that should the project fall behind schedule, Roadworthy will be assessed a penalty of $15 million for each year of delay. The discount rate on this project is 15%

a. Assuming the company completes the project on schedule, what is the present value of this project to the company?

b. If the company completes the project on time, what is the future value to the company at the end of the project (i.e., at the end of Year 3)?        

c. During the second year of construction, part of the bridge collapsed due to incorrect construction. Fortunately, the collapse occurred at night, and there were no injuries or casualties. However, new parts and equipment needed to be purchased, and the project had to restart from scratch. The adjusted schedule of completion of the entire project became

Year 3: 25%

Year 4: 75%

Year 5: 100%

Roadworthy would not be receiving any payment in Years 2 and 3, as payment has already been received for 25% completion of the project. If the company’s bridge construction went according to the new schedule, it would receive the next payment at the end of Year 4, and the last payment at the end of Year 5.

Furthermore, due to the delay in the project, the City of Edmonton will assess the company $15 million for each year of delay, with the penalties due at the end of Years 4 and 5.

What is the future value of this project at the end of Year 5?   

d. What is the minimum penalty that the city of Edmonton should charge Roadworthy in order to force it to complete the project by Year 4, with the following completion schedule?

Year 3: 50%

Year 4: 100%

(Hint: At the minimum penalty level, the future value of the project to the company will be $0 at end of Year 4.)

Reference no: EM131861506

Questions Cloud

Conduct a consumer analysis for the product : To conduct a consumer analysis for the product-the good, service, or idea-in your marketing plan: 1 Identify the consumers who are most likely to buy.
Create information and ideas in virtual communities : A premise of this model is that consumers carefully evaluate the merits and weaknesses of a given product when they consider .
How many futures contracts does this firm need to sell : Each futures contract is for 1,000 barrels. How many futures contracts does this firm need to sell or buy today to hedge the risk you defined above?
What is a buying center : What is a buying center? Describe the roles assumed by people in a buying center and what useful questions should be raised to guide any analysis.
Bridge building project in edmonton : Roadworthy Inc. is a bridge construction company. It has been contracted on a $75 million bridge building project in Edmonton.
How to improve the marketing effort behind new system : A firm that is marketing multimillion-dollar wastewater treatment systems to cities has been unable to sell a new type of system.
Are patents helpful in the process of developing : Mayo Clinic has filed an application for a broad method patent that gives it control over a new generation of treatments for chronic sinus inflammation.
Impact purchasing and paying habits of customers : The terms of sales and potential discounts or penalties can impact purchasing and paying habits of customers. How might this be so?
Write matlab program that prompts user for load impedance : Write a Matlab program that prompts the user for the following: Generator parameters, line characteristic impedance, line length, and load impedance

Reviews

Write a Review

Financial Management Questions & Answers

  Foreign company acquisition

Acquisition by a foreign company and the effects of that decision and the results of foreign exchange in Euro and the exchange rate differences.

  Financial management for profit and non profit organizations

In this essay, we are going to discuss the issues of financial management in a non-profit organisation.

  Method for estimating a venture''s value

Evaluate venture's present value, cash and surplus cash and basic venture capital.

  Replacement analysis

This document show the Replacement Analysis of modling machine. Is replacement give profit to company or not?

  Business finance task - capital budgeting

Your company is considering using the payback period for capital-budgeting. Discuss the advantages and disadvantages of this technique.

  Analysis of the investment

In this project, you will focus on one of these: the additional cost resulting from the purchase of an apple press (a piece of equipment required to manufacture apple juice).

  Conduct a what-if analysis

Review the readings and media for this unit, including the Anthony's Orchard case study media. Familiarise yourself with the Anthony's Orchard company and its current situation.

  Determine operational expenditures

Organisations' behaviour is guided by financial data. In the short term, such data will help determine operational expenditures; in the long term, historical data may help generate forecasts aimed at determining strategic plans. In both instances.

  Personal financial management

How much will you have left over each half year if you adopt the latter course of action?

  Sources of finance for expansion into new foreign markets

A quoted company is considering several long-term sources of finance for expansion into new foreign markets.

  Long term financial planning

This assignment is designed for analyze Long term financial planning begins with the sales forecast and the key input in the long term fincial planning.

  Explain the role of fincial manager

This assignment explain the role of fincial manager, function of manger. And what are the motives of financial manager.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd