Reference no: EM13321945
1. Which of the following is not one of the recommended guidelines for developing useful work package estimates?
A) Estimates should be made by those responsible for the work
B) Use several people to estimate the same work
C) Estimates should be based on normal conditions
D) Estimates should include a normal level of contingency
E) Estimates should be independent of other projects
2. Reasons why estimating time and cost are important include all of the following except:
A) To schedule work
B) To determine how long the project should take and cost
C) To develop cash flow needs
D) To determine how well the project is progressing
E) All of the above are valid reasons
3. Which of the following are not bottom-up approaches for estimating project times and costs?
A) Range Estimating
B) Parametric Procedures Applied to Specific Tasks
C) Consensus Methods
D) Appropriation Technique
E) Both C and D
4. As part of your project, you must develop Product Specifications. The fulfillment of this requirement is best typed as a(n) on your project network:
A) Event
B) Path
C) Activity
D) Node
E) Milestone.
Appear on a project scope checklist
: The lowest element in the hierarchical breakdown of the WBS is: "To construct a high-quality, custom home within five months at costs not to exceed $150,000" is best classified as: Which of the following is not one of the items that would appear on a..
|
Example of an organizational process asset
: Which one of the following is not an example of an Organizational Process Asset? The first step in creating the necessary information to manage a project is to: In Microsoft Project, if a resource is scheduled for more work - in a given time period -..
|
Calculate the total slack in an activity
: Which of the following will correctly calculate the total slack in an activity? If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first? Nodes on an AON project n..
|
The critical path in a project network represents
: The critical path in a project network represents the: Activities which can take place at the same time are termed: The backward pass in project network calculations determines the: The amount of time an activity can be delayed and yet not delay the ..
|
Bottom-up approaches for estimating project times and costs
: Which of the following are not bottom-up approaches for estimating project times and costs? Which of the following is not one of the recommended guidelines for developing useful work package estimates? Reasons why estimating time and cost are importa..
|
Quality of estimates for project times and costs
: Which of the following is provided by a project network but not by the work breakdown structure? On a project network, the activity times are derived from the: Which of the following is not one of the factors that need to be considered to improve qua..
|
What are potential benefits of recognizing
: What are potential benefits of recognizing and eliminating non-value added activities for businesses?
|
Describes the real value in his performances
: Robert Rauschenberg’s performance art can be said to be disjunctive and almost random. Which of the following statements best describes the real value in his performances?
|
Multi-weighted scoring models-Project life cycle
: Which of the following is not true of multi-weighted scoring models? Which of the following choices is not one of the stages of a project life cycle?
|