QUESTION ONE The Maxwell Construction Company

Assignment

(a) Draw a CPM network Diagram of the Project
(b) Perform the forward and back ward passes on the network and determine the Early & Late start and Early & late finish times for each activity. What is the total project duration?
(c) Calculate the total float for the project and identify all the critical activities and the critical path.
(d) Should the Maxwell Construction Company bid on the project?
(e) Discuss the advantages and Disadvantages of CPM as a planning and controlling technique.

QUESTION TWO

Manchester United Soccer Club

Assignment PART A
1. Make a list of the major deliverables for the project and use them to develop a draft of the work breakdown structure for the tournament that contains at least three levels of detail. What are the major deliverables associated with hosting an event such as a soccer tournament?
2. How would developing a WBS alleviate some of the problems that occurred during the first meeting and help Nicolette organize and plan the project?
3. Where can Nicolette find additional information to help her develop a WBS for the tournament?
4. How could Nicolette and her task force use the WBS to generate cost estimates for the tournament? Why would this be useful information?

PART B

The Manchester United Soccer Tournament project team has identified the following potential risks to their project:
a) Referees failing to show up at designated games.
b) Fighting between teams.
c) Pivotal error committed by a referee that determines the outcome of a game.
d) Abusive behavior along the sidelines by parents.
e) Inadequate parking.
f) Not enough teams sign up for different age brackets.
g) Serious injury.

How would you recommend that they respond (i.e., avoid, accept, . . .) to each of these risks and why?

QUESTION THREE

Your project is tasked with excavation of 1,000,000 cubic feet of soil. According to the project management plan you need to excavate 60,000 cubic feet of soil per week at a cost of $5 per cubic feet. According to the first month's progress report the project's EV was 1,000,000 and the AC was 1,200,000. According to the second month's progress report the project's EV was 2,200,000 and the AC was 4,400,000. After the 3rd month (12 weeks) you have 250,000 cubic feet of soil remaining to be excavated and you total cost to date is 4,000,000.

Determine the current values for the project for each of the terms below:

Term

Value

Budget At Completion

 

Planned Value

 

Earned Value

 

Actual Cost

 

Cost Variance

 

Schedule Variance

 

Cost Performance Index

 

Schedule Performance Index

 

Estimate At Completion

 

Estimate To Complete

 

Variance At Completion

 

Attachment:- Project And Contract Management.rar

Reference no: EM132504535

Questions Cloud

Find what would be the value of the bond : The bond will mature in 6 years. Current market yield for this bond is 7%. If the coupon is paid semi-annually, what would be the value of this bond?
Calculate the basic and diluted earnings per share : On September 30, 20X7, XYZ issued 100,000 ordinary shares for $1.5 million cash. Calculate the basic and diluted earnings per share figures for 20X7
What is the intrinsic value of the common stock : What is the intrinsic value of the common stock? The expected level of earnings at the end of this year (E1) is $6.00,The return on equity (ROE) is 15%
Realized gain or loss recognized on the income statement : What is the realized gain or loss recognized on the income statement using the fair value through OCI method? (Round all answers to the nearest dollar.)
BBA 490 Project And Contract Management Assignment : BBA 490 Project And Contract Management Assignment Help and Solution, School of Business, Economics And Management - Assessment Writing Service
Determine which operating segments are reportable : Sweet Corporation is divided into the following operating segments, Determine which operating segments are reportable under IFRS based on each of the following
What nominal rate of return : What nominal rate of return should you expect on a risk-free Finnish security?
How much money has the cash mgt system freed up : If the firm has P4 million per day in collection and P3 million per day in disbursements, how much money has the cash mgt system freed up?
Weighted average cost of capital-abc inc : ABC Inc.'s wants to fund a $5 million investment by using its $3 million of retained earnings and borrowing $2 million. ABC Inc.'s common shareholders

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd