Based on the material covered in class and using the following information about the activities of a project, please identify:

1. the shortest amount of time in which the project schedule can be crashed without exceeding $7K and

2. the project critical path that resulted from crashing the project

Activity

ID

Predecessor

Estimated Optimistic Time

Estimated Most

Likely Time

Estimated Pessimistic Time

Reduction

Time

Goal

Normal Costs

Costs of Reduction

a

-

15

20

85

10

$1,000

$867

b

a

25

40

235

20

$400

$262

c

b

60

100

500

140

$400

$347

d

a, b

25

30

125

25

$800

$560

e

c

45

50

145

45

$200

$120

f

e

30

50

220

65

$100

$53

g

d, f

20

30

130

15

$1,000

$1,600

Notes:

  • An activity should not be crashed if there is not a reduction in the duration of the project. Remember that crashing is investing financial resources to speed up the project. So why invest if there is not a reduction in the duration?
  • The term "Slope" creates some confusion with mathematical calculations of slope, which are different from what has been shown in the class. The "Slope" as discussed in class is really a "Ratio". You should calculate it using the equations taught in class, not the mathematical slope equation.
  • No partial crashing allowed
  • No optimality analysis allowed
  • The reduction is the amount of time we are seeking to gain from the originally estimated time.
  • "Cost of reduction" is the amount of money required to reduce the duration of the activity by the amount defined in "reduction time". In other words it is what we need to invest to reduce the duration of the activity.

Reference no: EM13382547

Questions Cloud

Topic - director have a primary duty to manage the company : topic - director have a primary duty to manage the company and not to answer to individual shareholders.note1.use
Duffy and thomas 1989 advocated that project reviews should : duffy and thomas 1989 advocated that project reviews should be 3-phases. pre-project reviews assess the feasibility of
I would like to examine in this weeks questions two : i would like to examine in this weeks questions two organizations that i have worked for. they will be similar in
In the words of mello 2010 corporate culture is the pattern : in the words of mello 2010 corporate culture is the pattern of shared values and norms which help individuals
Based on the material covered in class and using the : based on the material covered in class and using the following information about the activities of a project please
You have just been hired to manage a retail store located : you have just been hired to manage a retail store located in a small shopping center on the outskirts of a large city.
Conduct a comprehensive external environmental scan of your : conduct a comprehensive external environmental scan of your business unit including a five forces analysis to identify
Project management methodology implementation is strongly : project management methodology implementation is strongly affected by organizational culture mochal 2003 that it is why
Y-save is a big brand and name in the co-operative industry : y-save is a big brand and name in the co-operative industry in uganda. if anyone can name only ten of the many active

Reviews

Write a Review

Management Theories Questions & Answers

  Learning in action

Learning contract proposal that will form the basis of your learning contract report.

  Change is the only constant

"Change is the only constant " Evaluate the different types of change that have occurred in Sony.

  How do advertisers try to use group influence

How do advertisers try to use group influence?  Will you find any specific examples and explain the relevant theory of group behavior and influence?

  Case study:saving sony

You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.

  How the stock market works

The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.

  Find the optimal production quantities

Find not only the optimal production quantities, but also the optimal total cost.

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  Case study : bert''s bonsai and aquatic sport museum

Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.

  Knowledge management techniques

Demonstrate understanding of the many-sided nature of knowledge management

  Theory of transtheoretical model

Demonstrate understanding of the many-sided nature of knowledge management

  Write a paper on historical trends of management

Write a paper on Historical Trends of Management.

  Theory of reasoned action

Theory of Planned Behavior and Integrated Behaviors Model

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd