BA6052 Project Management Assignment

Assignment Help Project Management
Reference no: EM132584294

BA6052 Project Management - London Metropolitan University

BACKGROUND INFORMATION:

This case study is based on a job run by a firm of Computer Consultants to install some new database query software across a company with several different sites (nodes). The tasks are already grouped and indented - but resource allocations have been stripped out.

You can obtain the project file from WebLearn or from your BA6052 WebLearn site. The case study data file, called ‘BA6052.mpp', has been saved without a baseline.

Part A:

You are given the following information about the supply of resources for your project (all work based):

Resource Name:

Max Units:

Standard Rate

O/T rate:

Applications Manager

200%

£80.00/h

£95.00/h

Integration Manager

100%

£75.00/h

£90.00/h

Manager

100%

£80.00/h

£95.00/h

Network Engineer

600%

£50.00/h

£80.00/h

Programmer

500%

£50.00/h

£65.00/h

Software Installer

300%

£60.00/h

£80.00/h

Support Manager

100%

£60.00/h

£80.00/h

Systems Analyst

300%

£65.00/h

£85.00/h

System Tester

300%

£55.00/h

£70.00/h

Technical Author

100%

£70.00/h

£90.00/h

Required:

Part A i) 100% £70.00/h £90.00/h

First, allocate these resources to the tasks as stated below (where ‘NE' means ‘Network Engineer', ‘SA' means ‘Systems Analyst' ... and so on):

ID

Brief Name:

Resources to be allocated:

3

Install Ethernet and fast ethernet

NE at 200% and SA at 200%

4

Install multi mode fibre connection

NE at 100%

5

Request BT for connections

M at 100%

6

Schedule downtime for installation

NE at 200% and SA at 200%

9

Obtain Console hardware

SM at 100%

10

Determine subsystems to be installed

M at 100% and IM at 100%

Next, using your common sense (and differently from every other student), allocate at least one of the resources to each of the sub tasks as you consider appropriate. Do not add resources to top level summary tasks or milestones (though you may wish to add various fixed costs to these later).

For example, sub tasks that involve installation of software will require ‘Software Installers', sub tasks which involve writing or reviewing manuals will involve the ‘Technical Author', etc. Some sub tasks may need more than one resource. Do not feel that you have to use all of the resources listed.

For the first three such clashes that occur:
Resolve them in any way you consider sensible or let ‘MS Project' do it for you. Document carefully and explain any changes made either by you or by ‘MS Project' at the task level.

For any other clashes that occur:
Simply resolve them. There is no need to document any of the additional clashes.

Please note - as guidelines:

* With an acceptable allocation of resources (using the above tasks as guidelines for loadings), you should find that total costs are around £150,000 (possibly/probably a bit higher). You should not need to extend the duration of the project. If you do - you are probably loading in too many resources on each task. Try again.

* You are advised to choose the option for ‘Level within available slack' from the ‘Resource', ‘Levelling options' window and to show the baseline as a reference point via ‘Format'. You should also reset the baseline between clashes so as to collect the clearest possible evidence of each clash.

* Make sure that when you add resources to tasks you do so in a way that does not change task durations. Either allocate all the resources to a task at once or add the resources and then reset the duration in the ‘Gantt chart' to the original value.

* If you choose to solve clashes manually then remember that is it better to add new links between tasks rather than ‘dragging' them forward. Dragging a task sets an ‘SNET' constraint that may cause you problems later on.

* You may add other resources if you wish provided that you justify their inclusion.

Part A ii)

In part A i) above, you were given an initial supply of resources. Now that you have made your allocation of staff to tasks you should reconsider this initial allocation.

Required:

1. Find the minimum level of resources required for your project in order that it is still possible for all tasks to start at their earliest event times. Explain how you achieve this and give suitable evidence to show that it has been achieved.

2. Find the minimum number of ‘Network Engineers' that can be allocated without delaying the current project finish date. Again, explain and give evidence.

3. Explain also why this knowledge may be important to the effective management of your project

Leave the number of resources at the level found in ‘Part A ii) 1' for the rest of your work.

Part B:

You are now given the following information about various fixed costs:

Overheads are allocated to the project at £150 per day (covering management and administrative costs, secretarial support, consumables, photocopying, plan prints and office accommodation where allocated to this project, etc.). Payment is to be made pro rata.

For task 3 (Install ethernet and fast ...) the cost of components is £7000 paid up front.

For the duration of ‘Phase 2' you must hire a test site at a cost of £350 per week paid at the end of the phase.

Required:

Add the fixed costs as specified above. Describe carefully how each fixed costs is allocated within the programme and how much each adds to total cost. Provide evidence of these changes.

Of course, in the actual project, there would be far more fixed costs to take account of. But for the purposes of this assessment we will ignore them.

Note: When you add in fixed costs make sure you do so in a way that does not change the duration of your tasks.

Part C:

At the moment, by default, the project is using the ‘Standard' Microsoft Project calendar which ignores both Bank and Public Holidays. Create a new copy of the standard calendar (perhaps called by your name) and allocate it as the default calendar for your project. It should include the following dates, where relevant, as non working days:

Year 2021:

01 Jan

02 Apr

05 Apr

03 May

31 May

 

30 Aug

27 Dec

28 Dec

 

 

Note: if you are using your own project for the assessment and dates fall outside the range given above, then simply visit the ‘GOV.UK' (or any other) web page for dates:

With the ‘Standard' calendar the project is due to start on Monday, 08 March 2021 and finish on Monday, 18 June, 2021 (a total of 75 working days).

Required:

Where will your new calendar be used in Project? Carefully explain any change in the project finish date.

Show some clear evidence that your dates have been changed to non working days.

Part D:

What is meant by the term ‘tracking'? Why is it necessary to ‘track' a project?

Your project now starts and you receive a report telling you that tasks 3 to 7 went off exactly according to plan.

Required:

Update MS Project to show that tasks 3 to 7 did indeed go according to plan.

Now, track through this project for tasks 9 to 13 inclusive making any assumptions about actual durations and/or costs you like. Have at least three tasks where either the duration or the cost (or both) were different from your baseline figure(s).

Explain carefully the variances you introduce for each of the tasks and carefully document the impact on costs and durations in your project for each task.

Provide some print out which demonstrates that tracking has occurred at task level and shows any cost and/or time variances so created.

Attachment:- Project Management.rar

Reference no: EM132584294

Questions Cloud

Compute the balance of retained earnings at april : Compute the balance of Retained Earnings at April 30. (Decreases should be entered as a negative.) Issue common stock for cash, $10,000.
Defines leadership style : Create an outline and state which of five leadership styles (transformational, transactional, servant, laissez-fair, autocratic) best defines leadership style
How involved should the board of director : "How involved should the Board of Director be in an organization?" Is there any way that they can be too much involved??
What total amount of income from the investments should be : What total amount of income from the investments should be reported for the current year?How much is the cost of the qualifying asset on initial recognition?
BA6052 Project Management Assignment : BA6052 Project Management Assignment Help and Solution, London Metropolitan University - Assessment Writing Service - Find the minimum level of resources
What factors may lead to the development of gastritis : A 50-year-old man has been suffering from substernal pain for the last 5 months, particularly on waking up in the morning. He lost his job a year ago.
Assignment - Comparative Research Project : Assignment - Comparative Research Project. What are the main elements (parties, laws, processes) of the employment relations systems of these two countries
Establish ground rules for team operations : -Explain how a team leader might establish ground rules for team operations. What are the types of issues ground rules should relate to?
Implementation of the improvement program : Discuss issues to be considered with the implementation of the improvement program. Describe a desired outcome of the quality improvement plan.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd