Reference no: EM13757692
A manufacturer of high-quality small appliances intended for home use is currently working on the development of a new kitchen appliance that will chill foods quickly much as a microwave oven heats them quickly, although the technology involved is quite different. R&D engineers now have a working prototype and are satisfied that, with the cooperation from the production and marketing people, the product can be ready in time for the summer buying season. A target date has been set for product introduction that is 24 weeks away. One of the current issues for the company is that a competitor is also in the process of developing a similar product, which it intends to bring out at almost exactly the same time. The manager of the company is wondering whether it would be possible to expedite the usual product introduction process in order to beat the competition to the market. If possible, the manager would like to get a six week jump on the completion; this would put the product introduction date only 18 weeks away. Since the product of the company has been through the production-introduction process a number of times, the manager has developed a list of the tasks that must be accomplished and the order in which they must be completed. Although the duration and costs vary depending on the particular product, the basic process does not. The list of activities, the precedence relationships, activity durations, and costs estimates are presented in Table below. Note that some of the activities can be completed on crash basis, with an associated increase in cost. The company need to decide whether to bring the product to the market 18 weeks from now as the manager is recommending. For the project, indirect costs have been estimated at $5,500 per week. However, after week 18, if the product is not fully on the market, with each additional week the project investment value will reduce by $20,000. For every week the project is shortened – to week 18 – the manufacturer saves one week of investment value and indirect cost, or $25,500. For reduction beyond week 18, the savings are only the weekly indirect costs of $5,500. As the project manager specialist you have been asked to answer the following questions.
a. Develop an AON network diagram for the product and determine the number of paths and the critical path. How long does the project take using normal durations? What is the total cost required for completing the project on normal time?
b. Is it possible to complete the project in 18 weeks? What would the associated additional costs be? Which activities would need to be completed on a crash basis? What is the net savings from crashing the project to 18 weeks? What is the total cost required for completing the project in 18 weeks?
c. Is there some timeframe shorter than the 18 weeks recommended by the manager that would make sense in terms benefit-cost (i.e., what is the minimum-cost schedule?). What would be the total cost for completing in this timeframe?
d. What is the slack (in days) associated with noncritical paths through the project?
Calculate the unemployment rate
: The total number of workers who are officially unemployed consists of noninstitutionalized people aged 16 or older. Such workers are willing and are able to work and are actively looking for job but have not found a job.
|
A product mix is a product assortment
: A Product mix is a product assortment; Let's analyze the use of the word Length as opposed to Breadth. Are they really the same thing? Which term do you think captures the essence of its true meaning?
|
Select a law of the fifth discipline
: Select a Law of the Fifth Discipline we covered and discuss how you have seen, or experienced it’s success. Then select a second and different law, and discuss where you may have seen it, or are experiencing it currently, and how you might change the..
|
Describe the purpose of an acceptable use policy
: Describe the purpose of an Acceptable Use Policy you have selected and explain how the AUP helps provide confidentiality, integrity, and availability within the organization
|
Associated with noncritical paths through the project
: A manufacturer of high-quality small appliances intended for home use is currently working on the development of a new kitchen appliance that will chill foods quickly much as a microwave oven heats them quickly, although the technology involved is qu..
|
Assignment on beat the hacker
: A honeypot can be a useful for discovering some of the hacking trends occurring within an organization. Of course, there have to be certain measures placed upon its operation, maintenance, and the reconnaissance information obtained as a result. D..
|
Different components of security auditing architectre
: Explain different components of security auditing architecture. How is computer security influenced by Security awareness, training, and education
|
Find a turnaround strategy to maintain
: Evaluate why needing to have a competitive advantage is so highly recommended in the field of strategic management. Using an example of a specific organization, what might that organization do (or have they done) if they need to change or find a “tur..
|
Write essay on djkistrars algorithm
: Write Essay on Djkistrars Algorithm
|