Assignment: Project Schedule Changes
You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.
In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.
Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.
You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.
You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.
Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.
How the management practices of planning
: Explain how the management practices of planning, leading, organizing, staffing, and controlling are implemented in your workplace. If you are not currently working, you may use a previous employer.
|
Develop a strategic business plan for a new venture
: You are an administrative officer at the corporate level of an offshore organization and, you are assigned to develop a strategic business plan for a new venture in a sector of your choice.
|
Discuss the importance of work packages
: Discuss the importance of work packages to support the creation and use of the WBS. Examine how to establish a cost and schedule performance measurement baseline.
|
Standard of the overall research effort
: The standard of the overall research effort, including its quality and depth, with a range of suitable sources of different types required, such as books, journals, and Internet.
|
Assignment on the project schedule changes
: You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
|
Victim of stereotypes
: Have you been the victim of any stereotypes? What negative effects do stereotypes have on intercultural communication?
|
Write down the mathematical model as an lp
: Write down the mathematical model as an LP, Solve the problem using MS Excel Solver (submit only hard copies of the model and the solution sheet), Solve the problem with AMPL (submit hardcopies of the model, data and output files). You should use co..
|
Conducting an environmental analysis
: For all assignments assume that you are the administrator of a fictitious organization of your choice. The organization can be any type of health care organization such as a hospital, nursing home, rehabilitation center, clinic, etc.
|
Center for science in the public interest
: Background Information: The Center for Science in the Public Interest (CSPI) is a nonprofit education and advocacy organization that focuses on improving the safety and nutritional quality of our food supply.
|