Assignment on project schedule changes

Assignment Help Project Management
Reference no: EM13785655

Project Schedule Changes

You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.

You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.

In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.

Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.

You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.

You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.

Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.

 

Reference no: EM13785655

Questions Cloud

Find the ebit difference level associated : Find the EBIT difference level associated with tithe two financing plans - Prepare a pro forma statement for the EBIT level solved for in Part a. that shows that EPS will be the same regardless whether Plan A or B is chosen
Read critically and analyze the scenario provided : Read critically and analyze the scenario provided, Jill Jones is a bright 45-year-old woman who is the vice-president of sales in a mid-sized family owned Candy Corporation
Disease and natural disasters issues : Is this fact incompatible with the belief that there is an all-powerful God who cares about people? Why or why not?
Write an essay about college is a waste of time and money : Write an argumentative essay about "College is a Waste of Time and Money", "Why Colleges Shower Their Students with A's" and "Is Google Making Us Stupid?"
Assignment on project schedule changes : Project Schedule Changes .
What is the emotional effect of the objects : What is happening in the advertisement? Where does the scene take place - who are the people or subjects in the ad? What are they doing and what is the emotional effect of the objects/people in the image?
Explain why the courts decision was right or wrong : Explain why the Court's decision was right or wrong. Explain your argument and support it with examples or facts
Write a three pages essay research on causes bipolar disorde : Write a three pages essay research on causes and effects of bipolar disorder using "Siliver Lining Playbook" as the focus of the essay.
Personal reflection journal entry : adjusting to your life in terms of subjective well-being, diversity, contexts, and / or thinking critically. balancing your priorities, specifically with home, work, school, recreation, and / or family.

Reviews

Write a Review

Project Management Questions & Answers

  Construct a network diagram identify the critical paththe

construct a network diagram identify the critical paththe following data were obtained from a project to build a

  Techniques for risk identificationlist and describe two

techniques for risk identificationlist and describe two techniques for risk identification such as brainstorming a work

  We have developed a complete wbs that we feel truly defines

we have developed a complete wbs that we feel truly defines the scope of the project and it is well organized. we have

  The project scope describes what will be delivered as part

the project scope describes what will be delivered as part of the project and in some ways it can be likened to the

  Design and write a project plan for a well-known corporation

Design and write a project plan for a well-known corporation - select a project that you would like to see implemented within any well-known corporation

  The important location factors and ratings

The important location factors and ratings

  What are the four categories of consumer products

What are the four categories of consumer products? List and give an example of each.

  What operating cash flow does datums project generate each

what operating cash flow does datums project generate each year during its life?the datum co. has recently completed a

  Macrs calculations

MACRS calculations - what is the after-tax cash flow from the sale of machinery

  Evaluate the optimal production size for fertilizer

Evaluate the optimal production size for the fertilizer and evaluate the maximum inventory level

  The fixed costs associated with oven a

Oven type A can handle 25 pizzas per hour. the fixed costs associated with oven A are $10,000 and the variable costs are $2.00 per pizza

  Develop a communication plan

Prepare a project plan that covers all project groups and knowledge areas and separate tasks into sub-tasks, and a work package with stated durations and order of precedence.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd